Backstage Construction Schedule July 25 – 31, 2015
July 24, 2015 Leave a comment
This the construction schedule for 1 The Esplanade, Backstage condominium – for July 25 – 31, 2015.
NOTE: This week at Backstage work continues on interior suites with some major deliveries of key construction supplies.
Click on the link for a downloadable PDF July 25 – 31 Construction Summary: Backstage & L Tower Construction Summary-July 25-31-2015
Saturday, July 25
- Interior suite work: drywall and finishing.
- On-site housekeeping.
Monday, July 27
- Interior suite finishing all day.
Tuesday, July 28
- Interior suite finishing all day.
Wednesday, July 29
- Interior suite finishing all day.
- United drywall delivery in the morning.
- Kitchen materials delivery in the afternoon.
Thursday, July 30
- Interior suite finishing all day.
- Appliances will be delivered in the morning.
Friday, July 31
- Interior suite finishing all day.
- There will be carpentry and ventilation material deliveries in the morning.
NOTES:
- There may be some short-term impacts on pedestrian and vehicular traffic flow as delivery trucks are moved into and out of position.