Backstage Construction Schedule July 25 – 31, 2015

This the construction schedule for 1 The Esplanade, Backstage condominium – for July 25 – 31, 2015.

NOTE: This week at Backstage work continues on interior suites with some major deliveries of key construction supplies. 

 Click on the link for a downloadable PDF July 25 – 31 Construction Summary: Backstage & L Tower Construction Summary-July 25-31-2015

Backstage, L Tower, 25 The Esplanade & London on The Esplanade

Backstage, L Tower, 25 The Esplanade & London on The Esplanade

Saturday, July 25

  • Interior suite work: drywall and finishing.
  • On-site housekeeping.
Yonge and The Esplanade SE corner Backstage construction site.

Yonge and The Esplanade SE corner Backstage construction site.

Monday, July 27

  • Interior suite finishing all day.

Tuesday, July 28

  • Interior suite finishing all day. 

Wednesday, July 29

  • Interior suite finishing all day.
  • United drywall delivery in the morning.
  • Kitchen materials delivery in the afternoon.

Thursday, July 30

  • Interior suite finishing all day.
  • Appliances will be delivered in the morning.

Friday, July 31

  • Interior suite finishing all day.
  • There will be carpentry and ventilation material deliveries in the morning.
Backstage hoist July 24, 2015

Backstage hoist July 24, 2015

 NOTES:

    • There may be some short-term impacts on pedestrian and vehicular traffic flow as delivery trucks are moved into and out of position.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: