Backstage Construction Schedule July 18 – 24, 2015
July 18, 2015 Leave a comment
This the assumed construction schedule for 1 The Esplanade, Backstage condominium – for July 18 -24, 2015.
NOTE: This week Backstage work focuses on interiors and major deliveries of key construction supplies.
Click on the link for a downloadable PDF July 18 – 24 Construction Summary: Backstage & L Tower Construction Summary-July 18-24-2015
Saturday, July 18
- Interior suite work: drywall and finishing.
- On-site housekeeping.
Monday, July 20
- Interior suite finishing all day.
Tuesday, July 21
- Interior suite finishing all day.
- There will be a drywall delivery in the afternoon.
Wednesday, July 22
- Interior suite finishing all day.
- An 18th floor kitchen delivery in the morning.
- There will be a drywall delivery in the afternoon.
Thursday, July 23
- Interior suite finishing all day.
- Granite countertops delivery in the morning.e
- There will be a drywall delivery in the afternoon.
Friday, July 24
- Interior suite finishing all day.
- There will be carpentry and ventilation material deliveries in the morning.
NOTES:
- There may be some short-term impacts on pedestrian and vehicular traffic flow as delivery trucks are moved into and out of position.