Backstage Construction Schedule June 20 – 26, 2015
June 19, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for June 20 – 26, 2015.
NOTE: The focus at Backstage this week will be on interiors, especially kitchens and drywalling. Another relatively quiet week after the past three weeks.
Click on the link for a downloadable PDF June 20 – June 26 Construction Summary: Backstage & L Tower Construction Summary-June 20-26-2015
Saturday, June 20
- Interior suite work: drywall and finishing.
- On-site housekeeping.
Monday, June 22
- Interior suite finishing all day.
Tuesday, June 23
- Steel stud deliveries in the morning, at the south side of The Esplanade, east of Scott Street.
- Interior suite work: drywall and finishing.
Wednesday, June 24
- Kitchens cabinet deliveries in the morning, at the south side of The Esplanade, east of Scott Street.
- Drywall deliveries in the afternoon, at the south side of The Esplanade, east of Scott Street
- Interior suite work: drywall and finishing.
Thursday, June 25
- Interior suite finishing all day.
Friday, June 26
- Carpentry deliveries in the morning, at the south side of The Esplanade, east of Scott Street.
- Sheet metal deliveries in the morning, at the south side of The Esplanade, east of Scott Street.
- Interior suite work: drywall and finishing all day.
NOTES:
- There may be some short-term impacts on pedestrian and vehicular traffic flow as delivery trucks are moved into and out of position.