Backstage Construction Schedule June 13 – 19, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for June 13 – 19, 2015. 

NOTE: The focus at Backstage this week will be on interiors, especially kitchens and drywalling. A relatively quiet week after the past three weeks.  

Backstage Construction Detail, June 12 2015

Backstage Construction Detail, June 12 2015

Click on the link for a downloadable PDF June 13 – June 19 Construction Summary: Backstage & L Tower Construction Summary-June 13-19-2015

Kitchen island at Backstage

Kitchen island at Backstage

Saturday, June 13

  • Interior suite work: drywall and finishing.
  • On-site housekeeping.

Monday, June 15 

  • Interior suite finishing all day.

Tuesday, June 16

  • Countertop and drywall deliveries throughout the day at the south side of The Esplanade, east of Scott Street. 
  • Interior suite work: drywall and finishing.

Wednesday, June 17

  • Kitchens cabinet and steel stud deliveries throughout the day at the south side of The Esplanade, east of Scott Street. 
  • Interior suite work: drywall and finishing.

Thursday, June 18

  • Interior suite finishing all day.

Friday, June 19

  • Professional Carpentry deliveries after 7:00 am.
  • Interior suite work: drywall and finishing all day.
Kitchen in Backstage Suite

Kitchen in Backstage Suite

 NOTES:

    • There may be some short-term impacts on traffic flow as delivery trucks are moved into position.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: