Backstage Construction Schedule June 27 – July 3, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for June 27 – July 3, 2015. 

NOTE: Aecon will be on The Esplanade Monday and Tuesday installing Bell services, some traffic disruptions and noise should be expected. Otherwise the focus at Backstage this week will continue to be on interiors all week.  

Backstage interior construction

Backstage resident parking.

Click on the link for a downloadable PDF June 27 – July 3 Construction Summary: Backstage & L Tower Construction Summary-June 27-July 3-2015

Saturday, June 27

  • Interior suite work: drywall and finishing.
  • On-site housekeeping.
Backstage Interior construction 3

Backstage Interior Construction

Monday, June 29

  • Interior suite finishing all day.
  • Drywall deliveries in the afternoon, at the south side of The Esplanade, east of Scott Street.
  • Aecon will be on The Esplanade installing Bell services, some traffic disruptions and noise should be expected.

Tuesday, June 30

  • Aecon will be on The Esplanade installing Bell services, some traffic disruptions and noise should be expected. 
  • Interior suite work: drywall and finishing.

Wednesday, July 1 – Canada Day

  • SITE CLOSED for the national holiday. 

Thursday, July 2

  • Interior suite finishing all day.
  • Drywall deliveries in the afternoon, at the south side of The Esplanade, east of Scott Street.

Friday, July 3

  • Various trade deliveries all day, at the south side of The Esplanade, east of Scott Street
  • Interior suite finishing all day.
Backstage Interior construction 2

Backstage elevator shaft.

 NOTES:

    • There may be some short-term impacts on pedestrian and vehicular traffic flow as delivery trucks are moved into and out of position.

L Tower June 27 – July 3, 2015

8 The Esplanade – L Tower Saturday, June 27 – July 3, 2015.

  • REMINDER: The L Tower crane remains in place to facilitate the lift and placement of the rooftop window washing crane assembly and will remain up through the summer. 

Sidewalk work continues on the north side of The Esplanade as granite pavers are installed and edges are finished: 

New and improved Esplanade sidewalk

New and improved Esplanade sidewalk

 

Yonge & L Tower:

Yonge & L Tower

Yonge & L Tower

Backstage Construction Schedule June 20 – 26, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for June 20 – 26, 2015. 

NOTE: The focus at Backstage this week will be on interiors, especially kitchens and drywalling. Another relatively quiet week after the past three weeks.  

Backstage elevator shaft June 19, 2015

Looking down the Backstage elevator shaft June 19, 2015.

Click on the link for a downloadable PDF June 20 – June 26 Construction Summary: Backstage & L Tower Construction Summary-June 20-26-2015

Saturday, June 20

  • Interior suite work: drywall and finishing.
  • On-site housekeeping.
Backstage tower view, June 19, 2015

Backstage tower view, June 19, 2015

Monday, June 22 

  • Interior suite finishing all day.

Tuesday, June 23

  • Steel stud deliveries in the morning, at the south side of The Esplanade, east of Scott Street. 
  • Interior suite work: drywall and finishing.

Wednesday, June 24

  • Kitchens cabinet deliveries in the morning, at the south side of The Esplanade, east of Scott Street. 
  • Drywall deliveries in the afternoon, at the south side of The Esplanade, east of Scott Street
  • Interior suite work: drywall and finishing.

Thursday, June 25

  • Interior suite finishing all day.

Friday, June 26

  • Carpentry deliveries in the morning, at the south side of The Esplanade, east of Scott Street.
  • Sheet metal deliveries in the morning, at the south side of The Esplanade, east of Scott Street. 
  • Interior suite work: drywall and finishing all day.
Fall Protection Required Beyond This Point

Fall Protection Required Beyond This Point

 NOTES:

    • There may be some short-term impacts on pedestrian and vehicular traffic flow as delivery trucks are moved into and out of position.

L Tower June 20 – 26, 2015

8 The Esplanade – L Tower Saturday, June 20 – 26, 2015.

  • REMINDER: The L Tower crane remains in place to facilitate the lift and placement of the rooftop window washing crane assembly and will remain up through the summer. 

Sidewalk work continues on the north side of The Esplanade as granite pavers are installed. 

L Tower sidewalk work on The Esplanade

L Tower sidewalk work on The Esplanade

Sidewalk work continues on the north side of The Esplanade along the south side of the Sony Centre, east of the L Tower: 

Esplanade sidewalk work June 19, 2015

Esplanade sidewalk work June 19, 2015

 

Backstage Construction Schedule June 13 – 19, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for June 13 – 19, 2015. 

NOTE: The focus at Backstage this week will be on interiors, especially kitchens and drywalling. A relatively quiet week after the past three weeks.  

Backstage Construction Detail, June 12 2015

Backstage Construction Detail, June 12 2015

Click on the link for a downloadable PDF June 13 – June 19 Construction Summary: Backstage & L Tower Construction Summary-June 13-19-2015

Kitchen island at Backstage

Kitchen island at Backstage

Saturday, June 13

  • Interior suite work: drywall and finishing.
  • On-site housekeeping.

Monday, June 15 

  • Interior suite finishing all day.

Tuesday, June 16

  • Countertop and drywall deliveries throughout the day at the south side of The Esplanade, east of Scott Street. 
  • Interior suite work: drywall and finishing.

Wednesday, June 17

  • Kitchens cabinet and steel stud deliveries throughout the day at the south side of The Esplanade, east of Scott Street. 
  • Interior suite work: drywall and finishing.

Thursday, June 18

  • Interior suite finishing all day.

Friday, June 19

  • Professional Carpentry deliveries after 7:00 am.
  • Interior suite work: drywall and finishing all day.
Kitchen in Backstage Suite

Kitchen in Backstage Suite

 NOTES:

    • There may be some short-term impacts on traffic flow as delivery trucks are moved into position.

L Tower June 13 – 19, 2015

8 The Esplanade – L Tower Saturday, June 13 – 19, 2015.

  • REMINDER: The L Tower crane remains in place to facilitate the lift and placement of the rooftop window washing crane assembly and will remain up through the summer. 

 

L Tower with crane and temporary window washing platform

L Tower with crane and temporary window washing platform

Sidewalk work continues on the north side of The Esplanade and the east side of Yonge Street:

New Trees and Sidewalk on The Esplanade, June 12 2015

New Trees and Sidewalk on The Esplanade, June 12 2015

Yonge Street at L Tower, June 12, 2015

Yonge Street at L Tower, June 12, 2015

 

Backstage Construction Schedule June 6-12, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for June 6 – 12, 2015. 

NOTE: Cable Control Systems was delayed last week and will now be on site this week on The Esplanade digging trenches to lay cable for Rogers to service Backstage. The cable work will temporarily disrupt traffic along The Esplanade. Cable Control Systems will be applying for any relevant permits. 

Click on the link for a downloadable PDF June 6 – 12 Construction Summary: Backstage & L Tower Construction Summary-June 6-12-2015

Backstage suite kitchen June 5

Backstage suite kitchen June 5

Saturday, June 6

  • Interior suite work: drywall and finishing.
  • On-site housekeeping.

Monday, June 8 

  • Cable Control Systems for Rogers will be digging trenches for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems will be applying for any relevant permits. 
  • Interior suite finishing all day.
  • Toro Aluminum will be delivering windows for the roof. Their truck will occupy the south curb lane on The Esplanade from 8:00 am to approximately 12:00 pm.
  • Drywall delivery from 12:00 pm to 4:00 pm.

Tuesday, June 9

  • Cable Control Systems for Rogers will be digging trenches for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems will be applying for any relevant permits. 
  • Interior suite work: drywall and finishing.

Wednesday, June 10

  • Tile and Kitchen delivery after 7:00 am.
  • Drywall delivery after 12:00 pm
  • Interior suite work: drywall and finishing.

Thursday, June 11

  • Interior suite finishing all day.
  • Toro Aluminum will be delivering windows for the roof. Their truck will occupy the south curb lane on The Esplanade from 8:00 am to approximately 12:00 pm.

Friday, June 12

  • Cooltech and Professional Carpentry deliveries after 7:00 am.
  • Interior suite work: drywall and finishing all day.
Backstage interior work

Backstage interior work

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower June 6 – 12, 2015

8 The Esplanade – L Tower Saturday, June 6 – 12, 2015.

  • REMINDER: The L Tower crane remains in place to facilitate the lift and placement of the rooftop window washing crane assembly and will remain up through the balance of June. We will posting information in advance when a take-down and removal date is confirmed. 
L Tower June 5

L Tower June 5

  • Sidewalk work continues on the north side of The Esplanade 
Esplanade Sidewalk Construction June 5

Esplanade Sidewalk Construction June 5

 

 