L Tower May 30 – June 5, 2015

8 The Esplanade – L Tower Saturday, May 30 – June 5, 2015.

  • REMINDER: The L Tower crane remains in place to facilitate the lift and placement of the rooftop window washing crane assembly and will remain up through the balance of June. We will posting information in advance when a take-down and removal date is confirmed. 

    L Tower, 25 The Esplande, Sony Centre, Backstage

    L Tower, 25 The Esplande, Sony Centre, Backstage

  • Sidewalk work continues on the north side of The Esplanade 
    Building the new sidewalk at L Tower and Sony Centre

    Building the new sidewalk at L Tower and Sony Centre

    Sidewalk North Side of The Esplanade west of Scott Street

    Sidewalk North Side of The Esplanade west of Scott Street

  • The City of Toronto is continuing work on the Sony Centre’s north and east plaza:
City of Toronto work on the Sony Centre's north plaza.

City of Toronto work on the Sony Centre’s north plaza.

City of Toronto work progressing on the Sony Centre's northeast plaza.

City of Toronto work progressing on the Sony Centre’s northeast plaza.

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: