Backstage Construction Schedule May 30 – June 5, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 30 – June 5, 2015. 

NOTE: Cable Control Systems (for Rogers) and Distinct Tech (for Beanfeild) will be digging for incoming services to Backstage on June 2 – 4. The cable work will temporarily disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Backstage sans crane.

Backstage sans crane.

Click on the link for a downloadable PDF May 30 – June 5 Construction Summary: Backstage & L Tower Construction Summary-May 30-June 5-2015

South view from the 8th floor of Backstage

South view from the 8th floor of Backstage

Saturday, May 30

  • Interior suite work: drywall and finishing.
  • Exterior preparation work for cable laying next week with a mini excavator and breaker hammer, starting at 9:00 am.

Monday, June 1 

  • Interior suite finishing all day.
  • Toro railing delivery from 8:00 am to 12:00 pm.
  • Drywall delivery from 12:00 pm to 4:00 pm.

Tuesday, June 2

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 
  • Drywall delivery from 8:00 am to 12:00 pm
  • Interior suite work: drywall and finishing.

Wednesday, June 3

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Thursday, June 4

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Friday, June 5

  • Interior suite work: drywall and finishing all day.
Backstage interior work.

Backstage interior work.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: