8 The Esplanade – L Tower Saturday, May 9 – 15, 2015.
- Sidewalk work continues on the north side of The Esplanade
- The City of Toronto project to rebuild the north plaza of the Sony Centre is almost complete.
- The east sidewalk along Yonge Street at the L Tower is close to complete.
- REMINDER: The L Tower crane is currently scheduled to remain in place through June as it is required to facilitate the lift and placement of the rooftop window washing crane assembly.