Backstage Construction Schedule May 9 – 15, 2015
May 8, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 9 – 15, 2015.
Interior suite work, equipment material deliveries and podium deck clean-up are the main construction activities this week.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-May 9-15-2015
Saturday, May 9
- Interior suite work: drywall and finishing.
Monday, May 11
- Subcontractor Itlaform cleaning up materials the podium deck.
- Interior suite work: drywall and finishing.
Tuesday, May 12
- Delivery of the chiller to the site. Some short-term impacts on traffic will occur.
- Subcontractor Itlaform cleaning up materials the podium deck.
- Interior suite work: drywall and finishing.
Wednesday, May 13
- Subcontractor Itlaform cleaning up materials the podium deck.
- Interior suite work: drywall and finishing.
Thursday, May 14
- Interior suite work: drywall and finishing.
Friday, May 15
- Interior suite work: drywall and finishing.
NOTES:
- All rebar deliveries are now complete.
- A Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.