Backstage Construction Schedule May 2 – 8, 2015
May 1, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 2 – 8, 2015.
Work on the podium deck outdoor swimming pool, interior suite work and material deliveries are the main construction activities this week.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-May 2-8-2015
Saturday, May 2
- Interior suite work: drywall and finishing.
Monday, May 4
- Drywall delivery for the 17th Floor.
- Interior suite work: drywall and finishing.
Tuesday, May 5
- Delivery of roofing material.
- Interior suite work: drywall and finishing.
Wednesday, May 6
- Subcontractor Itlaform pouring concrete for the 5th floor outdoor swimming pool, from 1:00 pm.
- Interior suite work: drywall and finishing.
Thursday, May 7
- Interior suite work: drywall and finishing.
Friday, May 8
- Wood trim delivery from 7:00 am
- Interior suite work: drywall and finishing.
NOTES:
- All rebar deliveries are now complete.
- A Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.