Backstage Construction Schedule May 2 – 8, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 2 – 8, 2015. 

Work on the podium deck outdoor swimming pool, interior suite work and material deliveries are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-May 2-8-2015

Backstage podium deck - outdoor swimming pool

Backstage podium deck – outdoor swimming pool

Saturday, May 2

  • Interior suite work: drywall and finishing.

 Monday, May 4

  • Drywall delivery for the 17th Floor.
  • Interior suite work: drywall and finishing.

Tuesday, May 5

  • Delivery of roofing material.
  • Interior suite work: drywall and finishing.

Wednesday, May 6

  • Subcontractor Itlaform pouring concrete for the 5th floor outdoor swimming pool, from 1:00 pm.
  • Interior suite work: drywall and finishing.

Thursday, May 7

  • Interior suite work: drywall and finishing.

Friday, May 8

  • Wood trim delivery from 7:00 am
  • Interior suite work: drywall and finishing.
Backstage Interior with drywall

Backstage Interior with drywall

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: