Backstage Construction Schedule May 30 – June 5, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 30 – June 5, 2015. 

NOTE: Cable Control Systems (for Rogers) and Distinct Tech (for Beanfeild) will be digging for incoming services to Backstage on June 2 – 4. The cable work will temporarily disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Backstage sans crane.

Backstage sans crane.

Click on the link for a downloadable PDF May 30 – June 5 Construction Summary: Backstage & L Tower Construction Summary-May 30-June 5-2015

South view from the 8th floor of Backstage

South view from the 8th floor of Backstage

Saturday, May 30

  • Interior suite work: drywall and finishing.
  • Exterior preparation work for cable laying next week with a mini excavator and breaker hammer, starting at 9:00 am.

Monday, June 1 

  • Interior suite finishing all day.
  • Toro railing delivery from 8:00 am to 12:00 pm.
  • Drywall delivery from 12:00 pm to 4:00 pm.

Tuesday, June 2

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 
  • Drywall delivery from 8:00 am to 12:00 pm
  • Interior suite work: drywall and finishing.

Wednesday, June 3

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Thursday, June 4

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Friday, June 5

  • Interior suite work: drywall and finishing all day.
Backstage interior work.

Backstage interior work.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower May 30 – June 5, 2015

8 The Esplanade – L Tower Saturday, May 30 – June 5, 2015.

  • REMINDER: The L Tower crane remains in place to facilitate the lift and placement of the rooftop window washing crane assembly and will remain up through the balance of June. We will posting information in advance when a take-down and removal date is confirmed. 

    L Tower, 25 The Esplande, Sony Centre, Backstage

    L Tower, 25 The Esplande, Sony Centre, Backstage

  • Sidewalk work continues on the north side of The Esplanade 
    Building the new sidewalk at L Tower and Sony Centre

    Building the new sidewalk at L Tower and Sony Centre

    Sidewalk North Side of The Esplanade west of Scott Street

    Sidewalk North Side of The Esplanade west of Scott Street

  • The City of Toronto is continuing work on the Sony Centre’s north and east plaza:
City of Toronto work on the Sony Centre's north plaza.

City of Toronto work on the Sony Centre’s north plaza.

City of Toronto work progressing on the Sony Centre's northeast plaza.

City of Toronto work progressing on the Sony Centre’s northeast plaza.

 

Update Backstage Crane Removal May 26 – 28, 2015

Mobile crane equipment on The Esplanade preparing to set up for the Backstage tower crane removal, May 26.

Mobile crane equipment on The Esplanade preparing to set up for the Backstage tower crane removal, May 26.

During the crane removal work period May 26 – 28 the following impacts will occur:

  • Large tractor trailers may arrive as early 5:00 am due per Toronto Police Service restrictions on large loads travelling downtown during rush hour traffic.  
  • Work may start early and continue late as may be required to ensure the safe take down of the Backstage tower crane. Large crane work is exempt from City of Toronto Construction Noise Hours. ** (see below). 
  • When safety permits, every effort will be made to permit pedestrian access to Yonge Street. However it is prudent to plan on having to use Front Street East during some periods of the crane removal work. 
  • Paid Duty Officers will be on-site during the work. 
The Esplanade Road Closure at Church Street May 26 - 28

The Esplanade Road Closure at Church Street May 26 – 28

  • VEHICULAR ROAD CLOSURE: May 26, 27 & 28 the tower crane will be taken down from Backstage, The Esplanade will be closed to traffic from Yonge to the Novotel (east of Scott) from 7:00 am to 11:00 pm. 
  • Access to the St. Lawrence Garage west of Scott Street will be closed. 
  • There will be no vehicle access to The Esplanade from Scott Street (from 7:00 am to 11:00 pm). 
Mobile Crane setting up on The Esplanade May 26

Mobile Crane setting up on The Esplanade May 26

** TORONTO MUNICIPAL CODE  NOISE § 591-2.1 [Excerpt]

Construction. [Added 2007-12-13 by By-law No. 1400-2007]

(1) No person shall emit or cause or permit the emission of sound resulting from any operation of construction equipment or any construction, if it is clearly audible at a point of reception:

(a) In a quiet zone or residential area within the prohibited period of 7:00 p.m. one day to 7:00 a.m. the next day, 9:00 a.m. on Saturdays, and all day Sunday and statutory holidays; or

(b) In any other area within the prohibited period of all day Sunday and statutory holidays.

(2) Subsection B(1 a, b) does not apply to the continuous pouring of concrete, large crane work, necessary municipal work and emergency work that cannot be performed during regular business hours.

To read the full by-law please click on this link: http://www.toronto.ca/legdocs/municode/1184_591.pdf

Preliminary map of the May 26 - 28, Road Closure on The Esplanade

Preliminary map of the May 26 – 28, Road Closure on The Esplanade

Backstage Construction Schedule May 23 – 29, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 23 – 29, 2015. 

NOTICE: May 26, 27 & 28 the tower crane will be taken down from Backstage, The Esplanade will be closed to traffic from Yonge to the Novotel (east of Scott) from 7:00 am to 11:00 pm. There will be no access to Scott Street from The Esplanade. Pedestrian access to Yonge Street will be closed while the crane is taken down. 5 Paid Duty Police Officers will be on site to direct vehicular and pedestrian traffic. If and when safety permits, every effort will be made to permit pedestrian access to Yonge Street. However it is prudent to plan on having to use Front Street East during the crane removal work. 

Preliminary map of the May 26 - 28, Road Closure on The Esplanade

Preliminary map of the May 26 – 28, Road Closure on The Esplanade

Click on the link for a downloadable PDF May 23 – 29 Construction Summary: Backstage & L Tower Construction Summary-May 23-29-2015

May 26 – 28 City of Toronto Road Closure Permit: May 26 – 28 Road Closure Permit 13 The Esplanade St E

Backstage & L Tower Cranes as seen from Queen's Quay

Backstage & L Tower Cranes as seen from Queen’s Quay

Saturday, May 23

  • Interior suite work: drywall and finishing.
  • Site housekeeping work.

Monday, May 25 

  • Interior suite finishing all day.
  • Tile delivery from 8:00 am to 11:00 am.
  • Drywall delivery from 12:00 pm to 4:00 pm.

Tuesday, May 26

  • Dismantling tower crane, vehicular and pedestrian traffic on The Esplanade will be closed. There will be five (5) Paid Duty Police Officers on-site to direct vehicular and pedestrian traffic. Road Closure Permit Hours 7:00 am to 11:00 pm.
  • NOTE: Pedestrian access to Yonge Street on The Esplanade will be closed or restricted. However, every effort will be made to permit pedestrian access through the site when and if it is safe to do.
  • Interior suite work: drywall and finishing.

Wednesday, May 27

  • Dismantling tower crane, vehicular and pedestrian traffic on The Esplanade will be closed. There will be five (5) Paid Duty Police Officers on-site to direct vehicular and pedestrian traffic. Road Closure Permit Hours 7:00 am to 11:00 pm.
  • NOTE: Pedestrian access to Yonge Street on The Esplanade will be closed or restricted. However, every effort will be made to permit pedestrian access through the site when and if it is safe to do.
  • Interior suite work: drywall and finishing.

Thursday, May 28

  • Dismantling tower crane, vehicular and pedestrian traffic on The Esplanade will be closed. There will be five (5) Paid Duty Police Officers on-site to direct vehicular and pedestrian traffic. Road Closure Permit Hours 7:00 am to 11:00 pm.
  • NOTE: Pedestrian access to Yonge Street on The Esplanade will be closed or restricted. However, every effort will be made to permit pedestrian access through the site when and if it is safe to do.
  • Interior suite work: drywall and finishing.

Friday, May 29

  • Interior suite work: drywall and finishing all day.
  • Kitchen delivery from 8:00 am to 10:00 am
  • Toro Railing delivery from 10:00 am to 12:00 pm
View northwest from the 8th floor of Backstage

View northwest from the 8th floor of Backstage

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower May 23 – 29, 2015

8 The Esplanade – L Tower Saturday, May 23 – 29, 2015.

  • REMINDER: The L Tower crane remains in place to facilitate the lift and placement of the rooftop window washing crane assembly and it may be used to assist this week to help take down the Backstage tower crane.
L Tower Crane and L Tower

L Tower Crane and L Tower

  • Sidewalk work continues on the north side of The Esplanade 
L Tower sidewalk work on The Esplanade east of Yonge

L Tower sidewalk work on The Esplanade east of Yonge

Advance Notice: Esplanade Road Closure May 26 – 28, 2015

NOTICE: Road Closure May 26, 27 & 28 2015

For the Backstage Tower Crane Removal

  • The Esplanade Yonge to the Novotel (east of Scott).
  • Lower Scott Street will also be closed traffic.
  • No pedestrian access to Yonge Street when
    the Backstage crane is being taken down.
Preliminary map of the May 26 - 28, Road Closure on The Esplanade

Preliminary map of the May 26 – 28, Road Closure on The Esplanade

  • The City of Toronto will be issuing a road closure
    permit as of May 19.
  • Notices will be delivered to local residents and
  • Detailed information and updates will be posted on this website. 

Please click on the link to download a PDF of this notice: The Esplanade May 2015 Road Closure

Backstage Construction Schedule May 16 – 22, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 16 – 22, 2015. 

ADVANCE NOTICE: May 26, 27 & 28 the tower crane will be taken down from Backstage, The Esplanade will be closed to traffic from Yonge to the Novotel (east of Scott) and there will be no access to Scott Street from The Esplanade. Pedestrian access to Yonge Street will be closed while the crane is taken down. Please click here for more information. 

Click on the link for a downloadable PDF May 16 – 22 Construction Summary: Backstage & L Tower Construction Summary-May 16-22-2015

Backstage tower crane, to be removed May 26 - 27

Backstage tower crane, to be removed May 26 – 27

Saturday, May 16

  • Interior suite work: drywall and finishing.

MONDAYVICTORIA DAY – site closed 

Looking up the elevator shaft at Backstage

Looking up the elevator shaft at Backstage

Tuesday, May 19

  • Steel stud delivery for 19th floor, from 8:00 am to 12:00 pm 
  • Drywall delivery, from 1:00 pm to 4:00 pm
  • Interior suite work: drywall and finishing.

Wednesday, May 20

  • Interior suite work: drywall and finishing.

Thursday, May 21

  • Interior suite work: drywall and finishing.
  • Kitchen delivery for the 9th and 10th floors.

Friday, May 22

  • Interior suite work: drywall and finishing.
Suites coming together at Backstage

Suites coming together at Backstage

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower May 16 – 22, 2015

8 The Esplanade – L Tower Saturday, May 16 – 22, 2015.

  • Sidewalk work continues on the north side of The Esplanade 
Building the new sidewalk on the south edge of the Sony Centre, May 14

Building the new sidewalk on the south edge of the Sony Centre, May 14

Esplanade sidewalk work at L Tower May 14

Esplanade sidewalk work at L Tower, May 14

 

  • REMINDER: The L Tower crane is currently scheduled to remain in place through June as it is required to facilitate the lift and placement of the rooftop window washing crane assembly.
L Tower Crane. May 14, 2015

L Tower Crane. May 14, 2015

Backstage Construction Schedule May 9 – 15, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 9 – 15, 2015. 

Interior suite work, equipment material deliveries and podium deck clean-up are the main construction activities this week.

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-May 9-15-2015

8th Floor balcony view from Backstage, looking west to Union Station and the CN Tower.

8th Floor balcony view from Backstage, looking west to Union Station and the CN Tower.

Saturday, May 9

  • Interior suite work: drywall and finishing.

 

8th Floor suite at Backstage, facing north.

8th Floor suite at Backstage, facing north.

Monday, May 11

  • Subcontractor Itlaform cleaning up materials the podium deck.
  • Interior suite work: drywall and finishing.

Tuesday, May 12

  • Delivery of the chiller to the site. Some short-term impacts on traffic will occur.
  • Subcontractor Itlaform cleaning up materials the podium deck.
  • Interior suite work: drywall and finishing.
Outdoor pool at Backstage on the podium roof deck.

Outdoor pool at Backstage on the podium roof deck.

Wednesday, May 13

  • Subcontractor Itlaform cleaning up materials the podium deck.
  • Interior suite work: drywall and finishing.

Thursday, May 14

  • Interior suite work: drywall and finishing.

Friday, May 15

  • Interior suite work: drywall and finishing.
8th Floor suite at Backstage facing west.

8th Floor suite at Backstage facing west.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower May 9 – 15, 2015

8 The Esplanade – L Tower Saturday, May 9 – 15, 2015.

  • Sidewalk work continues on the north side of The Esplanade 
L Tower Sidewalk Work just east of Yonge

L Tower Sidewalk Work just east of Yonge

Sidewalk work at L Tower on The Esplanade

Sidewalk work at L Tower on The Esplanade

 

  • The City of Toronto project to rebuild the north plaza of the Sony Centre is almost complete. 
Front Street Sony Centre North Plaza

Front Street Sony Centre North Plaza

  • The east sidewalk along Yonge Street at the L Tower is close to complete.

 

Yonge Street at L Tower

Yonge Street at L Tower

  • REMINDER: The L Tower crane is currently scheduled to remain in place through June as it is required to facilitate the lift and placement of the rooftop window washing crane assembly.