Backstage Construction Schedule April 25 – May 1, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 25 – May 1, 2015. 

Work on the podium deck outdoor swimming pool and interior suite drywall work are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-25-May 1-2015

South side of Backstage at the railway tracks

South side of Backstage at the railway tracks

Saturday, April 25

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.

 Monday, April 27

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.

Tuesday, April 28

  • Subcontractor Itlaform starting a concrete pour for the5th floor outdoor swimming pool starting at 10:00am.
  • Interior suite drywall and finishing.

Wednesday, April 29

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.

Thursday, April 30

  • Subcontractor Itlaform starting a concrete pour for the5th floor outdoor swimming pool starting at 10:00am.
  • Interior suite drywall and finishing.

Friday, May 1

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.
Interior future gallery : PATH space at Backstage

Interior future gallery : PATH space at Backstage

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: