Backstage Construction Schedule April 20 – 24, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 20 – 24, 2015. 

Work on the podium deck outdoor swimming pool and interior suite drywall work are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-20-24-2015

Backstage swimming pool on the podium deck

Backstage swimming pool on the podium deck

 Monday, April 20

  • Drywall delivery from 8:00 am to 1:00 pm.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.

Tuesday, April 21

  • Concrete pour for the podium deck swimming pool starting at 11:00am, concrete finishing till 9:00pm
  • Interior suite drywall and finishing.
  • Waterproofing 5th floor podium.

Wednesday, April 22

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.

Thursday, April 23

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.

Friday, April 24

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.
Yonge Street Railway Bridge - future PATH connection to Union Station.

Yonge Street Railway Bridge – future PATH connection to Union Station.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: