Backstage Construction Schedule April 25 – May 1, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 25 – May 1, 2015. 

Work on the podium deck outdoor swimming pool and interior suite drywall work are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-25-May 1-2015

South side of Backstage at the railway tracks

South side of Backstage at the railway tracks

Saturday, April 25

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.

 Monday, April 27

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.

Tuesday, April 28

  • Subcontractor Itlaform starting a concrete pour for the5th floor outdoor swimming pool starting at 10:00am.
  • Interior suite drywall and finishing.

Wednesday, April 29

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.

Thursday, April 30

  • Subcontractor Itlaform starting a concrete pour for the5th floor outdoor swimming pool starting at 10:00am.
  • Interior suite drywall and finishing.

Friday, May 1

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.
Interior future gallery : PATH space at Backstage

Interior future gallery : PATH space at Backstage

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower April 25 – May 1, 2015

8 The Esplanade – L Tower Saturday, April 25 – 2May 1, 2015.

  • The L Tower crane, seen here from Scott Street continues to be used. Also note the temporary platform for the window washing crane at the top of the tower. We expect it will remain up through May. 
  •  The L Tower is now the second most photographed building in Toronto after the CN Tower. Here is another view of it from Front Street East.
L Tower from Front Street East

L Tower from Front Street East

The Esplanade looking east from Yonge

The Esplanade looking east from Yonge

 

Backstage Construction Schedule April 20 – 24, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 20 – 24, 2015. 

Work on the podium deck outdoor swimming pool and interior suite drywall work are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-20-24-2015

Backstage swimming pool on the podium deck

Backstage swimming pool on the podium deck

 Monday, April 20

  • Drywall delivery from 8:00 am to 1:00 pm.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.

Tuesday, April 21

  • Concrete pour for the podium deck swimming pool starting at 11:00am, concrete finishing till 9:00pm
  • Interior suite drywall and finishing.
  • Waterproofing 5th floor podium.

Wednesday, April 22

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.

Thursday, April 23

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.

Friday, April 24

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.
Yonge Street Railway Bridge - future PATH connection to Union Station.

Yonge Street Railway Bridge – future PATH connection to Union Station.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower April 18 – 24, 2015

8 The Esplanade – L Tower Saturday, April 18 – 24, 2015.

  • The L Tower crane, seen here from Scott Street continues to be used. Also note the temporary platform for the window washing crane at the top of the tower. 
L Tower looking south from Scott & Colborne

L Tower looking south from Scott & Colborne

  • The entrance to the L Tower continues to take shape.
L Tower entrance at 8 The Esplanade

L Tower entrance at 8 The Esplanade

  •  The L Tower is now the second most photographed building in Toronto after the CN Tower. Here it is as seen from Front Street.
L Tower from Front & Church

L Tower from Front & Church

 

Backstage Construction Schedule April 18, 2015

Saturday schedule for 1 The Esplanade, Backstage condominium – April 18, 2015.   

  • Interior work, drywall and fitting out suites.
  • Forming the swimming pool on the podium deck
  • General housekeeping work on the site.
Backstage Interior Unit Work

Backstage Interior Unit Work

 

The construction schedule for April 20 – 24 will be posted prior to 7:00 am April 20. Please check back for details. 

Backstage Construction Schedule April 13 – 17, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 13 – 17, 2015. 

Last concrete pour for the tower and work on the podium deck outdoor swimming pool are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-13-17-2015

Backstage Swimming Pool on the Podium Deck looking east from the tower.

Backstage Swimming Pool on the Podium Deck looking east from the tower.

 Monday, April 13

  • Last concrete pour for the tower, elevator curbs on the roof (8 meters of concrete), starting at 12:00 pm. 
  • Interior suite drywall and finishing.

Tuesday, April 14

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.
  • 35th floor Window delivery occupying north curb lane of the Esplanade, starting at 2:00 pm to approximately 4:00 pm.

Wednesday, April 15

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.

Thursday, April 16

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.

Friday, April 17

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.
Backstage tower south west elevation

Backstage tower south west elevation

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower April 11 – 17, 2015

8 The Esplanade – L Tower Saturday, April 11 – 17, 2015.

  • The granite pavers are being laid at the entrance to the L Tower.
L Tower Granite Pavers

L Tower Granite Pavers

  • The Yonge Street sidewalk continues to take shape.
L Tower Yonge Street sidewalk taking shape

L Tower Yonge Street sidewalk taking shape

 

  • The L Tower crane, seen here from the 8th floor of the Backstage condominium, continues to be used, . As of now we expect it to be taken down at the end of April. We will provide updates as we get them.
L Tower crane seen from the Backstage condo

L Tower crane seen from the Backstage condo

  • The L Tower is now the second most photographed building in Toronto after the CN Tower. Here it is as seen from The Esplanade and Berkeley Street.
L Tower from The Esplanade

L Tower from The Esplanade

 

Backstage Construction Schedule April 11, 2015

Saturday schedule for 1 The Esplanade, Backstage condominium – April 11, 2015.   

  • Interior work will be the focus on Saturday April 11. The interior suites are starting to come together as drywall goes up and elements, such as bathtubs, are installed.
Backstage 8th floor condo interior

Backstage 8th floor condo interior

Backstage 8th floor suite interior

Backstage 8th floor suite interior

Backstage 8th floor interior

Backstage 8th floor interior, looking south.

 

The construction schedule for April 13 – 17 will be posted prior to 7:00 am April 13. Please check back for details. 

Backstage Construction Schedule April 4 – 10, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 4 – 10, 2015.   More concrete pours for the roof and more window deliveries are the featured construction activities this week. 

Backstage podium deck April 2

Backstage podium deck showing the swimming pool liner, April 2, 2015

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-4-10-2015

Saturday, April 4

  • No Construction Work is Scheduled. 

Monday, April 6

  • Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm. 
  •  Interior suite drywall and finishing.
  •  Waterproofing 5th floor podium.

Tuesday, April 7

  • Drywall deliveries for the 13th floor, from 8:00 am to 1:00 pm.
  • Elevator machine room roof  concrete pour by subcontractor Italform (35meters of concrete), starting at 11:00 am.
  • Waterproofing 5th floor podium.
  • Concrete finishing till 10:00 pm

Wednesday, April 8

  • Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm. 
  •  Interior suite drywall and finishing.
  •  Starting swimming pool work on the  5th floor podium.

Thursday, April 9

  • Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm. 
  •  Interior suite drywall and finishing.
  •  Continuing swimming pool work on the  5th floor podium.

Friday, April 10

  • Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm. 
  • Interior suite drywall and finishing.
  • Continuing swimming pool work on the  5th floor podium.
Backstage interior 13th floor.

Backstage interior 13th floor.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower April 4 – 10, 2015

8 The Esplanade – L Tower Saturday, April 4 – 10, 2015.

  • The City of Toronto is currently renovating and redesigning and rebuilding the north plaza and entrance way to the Sony Centre for the Performing Arts. This work is separate from the Plaza project. The first pahse of work, depicted below, should be complete within a week to 10 days. 
L Tower from Front & Scott Street

L Tower from Front & Scott Street

City of Toronto Front Street sidewalk reconstruction at the Sony Centre

City of Toronto Front Street sidewalk reconstruction at the Sony Centre

  • The eastbound traffic lane of The Esplanade, will be open over the Easter/Passover weekend.
L Tower entrance at Yonge & The Esplanade

L Tower entrance at Yonge & The Esplanade

  • The L Tower crane continues to be used. As of now we expect it to be taken down at the end of April. We will provide updates as we get them.
L Tower from Yonge Street & Adelaide

L Tower from Yonge Street & Adelaide