Backstage Construction Schedule April 25 – May 1, 2015
April 24, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 25 – May 1, 2015.
Work on the podium deck outdoor swimming pool and interior suite drywall work are the main construction activities this week.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-25-May 1-2015
Saturday, April 25
- Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
- Interior suite drywall and finishing.
Monday, April 27
- Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
- Interior suite drywall and finishing.
Tuesday, April 28
- Subcontractor Itlaform starting a concrete pour for the5th floor outdoor swimming pool starting at 10:00am.
- Interior suite drywall and finishing.
Wednesday, April 29
- Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
- Interior suite drywall and finishing.
Thursday, April 30
- Subcontractor Itlaform starting a concrete pour for the5th floor outdoor swimming pool starting at 10:00am.
- Interior suite drywall and finishing.
Friday, May 1
- Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
- Interior suite drywall and finishing.
NOTES:
- All rebar deliveries are now complete.
- A Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.