Backstage Construction Schedule March 28 – April 3, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for March 28 – April 3, 2015.   More concrete pours for the roof and more window deliveries are the featured construction activities this week. 

Backstage Condo Rooftop

Backstage Condo Rooftop

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Mar-28-Apr-3-2015

Saturday, March 28

  • Window delivery occupying north curb lane of the Esplanade, three tractor trail loads, from 9:00 am to 2:30 pm.
  • We have been advised that the City of Toronto will  be carrying out road repair and resurfacing on The Esplanade.
Backstage Condo March 27

Backstage Condo March 27

Monday, March 30

  • Mechanical roof concrete pour #2 & #3, by subcontractor Italform, to begin at 10:30 am.
  • Concrete Finishing until 10:30 pm.

Tuesday, March 31

  •  Pouring curbs on the mechanical roof (9 metres of concrete), by subcontractor Italformscheduled to run from 2:30 pm.

Wednesday, April 1

  • Concrete pour for the elevator machine room roof (30 metres of concrete), by subcontractor Italform, to begin at 10:30 am.
  • Concrete Finishing until 10:30 pm.

Thursday, April 2

  • Pouring curbs on the mechanical roof (9 metres of concrete), by subcontractor Italform, scheduled to run from 2:30 pm.

Friday, April 3

  • TBA.
Backstage Concrete Truck March 27

Backstage Concrete Truck March 27

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: