Backstage Construction Schedule March 14 – 20, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for March 14 – 20, 2015.   Protective platforms are coming down this Saturday and secondary slab and wall and column concrete pours continue through the week.

Drywall waiting to go up at Backstage

Drywall waiting to go up at Backstage

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Mar-14-20-2015

Saturday, March 14

  • Subcontractor Italform will be removing three (3) protection platforms from the south side of the building, facing the railway corridor. Three (3) tractor trails will be required to transport.
  • The first trailer will arrive at 11:00 am.
  • The second trailer at 1:00 pm, and
  • The third trailer at 2:00 pm.
  • Most of the work will take place on the 5th floor podium and then loaded on to trailers.

Monday, March 16

  • A wall and column concrete pour, by subcontractor Italform (14 metres of concrete), scheduled to run from 1:30 pm.

Tuesday, March 17

  • Secondary slab concrete pour #1, by subcontractor Italform, to begin today at 11:30 am.
  • A wall and column concrete pour, by subcontractor Italform (9 metres of concrete), scheduled to run from 1:30 pm.
  • Concrete Finishing until 10:30 pm.

Wednesday, March 18

  • Secondary slab concrete pour #2, by subcontractor Italform, to begin today at 11:30 am.
  • A wall and column concrete pour, by subcontractor Italform (14 metres of concrete), scheduled to run from 1:30 pm.
  • Concrete Finishing until 10:30 pm.

Thursday, March 19

  • A wall and column concrete pour, by subcontractor Italform (20 metres of concrete), scheduled to run from 1:30 pm.

Friday, March 20 A wall and column concrete pour, by subcontractor Italform (12 metres of concrete), scheduled to run from 1:30 pm.

Pouring concrete at Backstage on Friday the 13th of March

Pouring concrete at Backstage on Friday the 13th of March

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: