Backstage Construction Schedule March 9 – 13
March 8, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for March 7 – 13, 2015.
Concrete pours for the ROOF slab began last week and should be completed. Weather, though milder, may once again affect the construction schedule. Please check back for regular updates.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Mar-9-13-2015
Monday, March 9
- Rebar delivery scheduled to run from 7:00 am.
- A wall and column concrete pour, by subcontractor Italform (15 metres of concrete), scheduled to run from 12:30 pm.
Tuesday, March 10
- ROOF slab concrete pour #3, by subcontractor Italform, to begin today at 10:30 am.
- Concrete Finishing until 11:30 pm.
Wednesday, March 11
- A wall and column concrete pour, by subcontractor Italform (34 metres of concrete), scheduled to run from 12:30 pm.
Thursday, March 12
- A wall and column concrete pour, by subcontractor Italform (22 metres of concrete), scheduled to run from 12:30 pm.
Friday, March 13
- A wall and column concrete pour, by subcontractor Italform (18 metres of concrete), scheduled to run from 12:30 pm.
NOTES:
- A Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.