Backstage Construction Schedule March 28 – April 3, 2015
March 27, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for March 28 – April 3, 2015. More concrete pours for the roof and more window deliveries are the featured construction activities this week.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Mar-28-Apr-3-2015
Saturday, March 28
- Window delivery occupying north curb lane of the Esplanade, three tractor trail loads, from 9:00 am to 2:30 pm.
- We have been advised that the City of Toronto will be carrying out road repair and resurfacing on The Esplanade.
Monday, March 30
- Mechanical roof concrete pour #2 & #3, by subcontractor Italform, to begin at 10:30 am.
- Concrete Finishing until 10:30 pm.
Tuesday, March 31
- Pouring curbs on the mechanical roof (9 metres of concrete), by subcontractor Italform, scheduled to run from 2:30 pm.
Wednesday, April 1
- Concrete pour for the elevator machine room roof (30 metres of concrete), by subcontractor Italform, to begin at 10:30 am.
- Concrete Finishing until 10:30 pm.
Thursday, April 2
- Pouring curbs on the mechanical roof (9 metres of concrete), by subcontractor Italform, scheduled to run from 2:30 pm.
Friday, April 3
- TBA.
NOTES:
- All rebar deliveries are now complete.
- A Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.