Backstage Construction Schedule February 23 – 27, 2015
February 23, 2015 Leave a comment
This is the REVISED construction schedule for 1 The Esplanade, Backstage condominium – for February 23 – 27, 2015.
UPDATED: Concrete pours for the ROOF slab may now begin this Friday. Extreme weather may once again affect the construction schedule. Please check back for regular updates.
Click on the link for a downloadable PDF Construction Summary: Revised-Backstage & L Tower Construction Summary-Feb-23-27-2015
Monday, February 23
- CANCELLED due to weather: A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.
Tuesday, February 24
- A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.
Wednesday, February 25
- A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.
Thursday, February 26
- Rebar deliveries starting at 7 am
- A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.
Friday, February 27
- Tentative: 36th Floor slab concrete pour #3, by subcontractor Italform, may begin today at 11:00 am.
- Tentative: After slab, wall & column pour (35 metres of concrete).
- Tentative: Concrete Finishing until to 11:30 pm.
NOTES:
- A Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.