Backstage Construction Schedule February 17 – 20, 2015
February 16, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for February 17 – 20, 2015.
Note: Concrete pours for the 36th Floor slab did begin last week but once again were interrupted by severe weather. With any luck from mother nature, the 36th floor should be completed this week. Please check back for regular updates.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Feb-17-20-2015
There was no work on site on Monday, February 16 as crews were off for the Family Day Holiday.
Tuesday, February 17
- 36th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 11:00 am.
- After slab, wall & column pour (53 metres of concrete).
- Concrete Finishing until to 11:30 pm.
Wednesday, February 18
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Thursday, February 19
- A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.
Friday, February 20
- A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.
NOTES:
- A Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.