8 The Esplanade – L Tower Saturday, February 14, 2015 – Sunday, February 22, 2015.
New residents move in every week to the L Tower. Sidewalk work will resume once temperatures moderate sufficiently to permit it.
Tower Crane Operator Rob Mac AKA @SkyJacked793 continues to take great pictures that he shares on his twitter feed.
- Interior work continues on multiple floors.
- Move-ins are ongoing through the Yonge Street entrance.
- Valet parking for L Tower residents continues on the north side of The Esplanade, west of Scott Street.
LOOKING AHEAD:
- Update: The Large Crane Tower was scheduled to remain in place over the winter and be removed in March, it now may not be removed until April.
- Update: the Sony Centre Plaza is now scheduled to be completed by June 2015, prior to the Pan Am Games.
Yet one more delay, without any real reasoning why. The units are all already sold, but does this ever speak to the quality/reliability of the builder.
We’re not sure delay you are speaking of? We have noted that the impact of severe cold on pouring concrete at Backstage. L Tower is substantially complete and residents are moving in every day. Sadly the cold weather is not something any builder can solve.