This is the current construction schedule for 1 The Esplanade, Backstage condominium – for Saturday, February 14, 2015.
Note: Extreme cold weather continues to cause delays and rescheduling of concrete pours and deliveries.

The current Backstage “construction streetscape” will be replaced by a broad sidewalk, trees, animated by retail and the entrance to the new public exhibit space on the 2nd floor.
Saturday, February 14
- Weather permitting, a window delivery is scheduled to bring window and glazing for 2 floors, starting at 9:00am.
The construction schedule for Monday, February 16 – Friday, February 20 was not available at post time. We will post that information by Tuesday morning. Please check back.