L Tower February 7 – 13, 2015
February 6, 2015 Leave a comment
8 The Esplanade – L Tower Saturday, Saturday, February 7, 2015 – Friday, February 13
New neighbourhood residents are occupying their as move-ins continue to the L Tower. Sidewalk work will resume once temperatures moderate.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Feb-7-13-2015
- Interior work continues on multiple floors.
- Move-ins are ongoing through the Yonge Street entrance.
- Sidewalk work will continue as when conditions improve.
- Valet parking for L Tower residents continues on the north side of The Esplanade, west of Scott Street.
LOOKING AHEAD:
- Update: The Large Crane Tower was scheduled to remain in place over the winter and be removed in March, it now may not be removed until April.
- Update: the Sony Centre Plaza is now scheduled to be completed by June 2015, prior to the Pan Am Games.