L Tower Update January 24 – 30, 2015
January 23, 2015 Leave a comment
8 The Esplanade – L Tower Saturday, Saturday, January 24, 2015 – Friday, January 30
New neighbourhood residents are occupying their as move-ins continue to the L Tower. Streetscape improvements continue as weather permits.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-24-30-2015
- Interior work continues on multiple floors.
- Move-ins are ongoing through the Yonge Street entrance.
- Sidewalk work will continue as weather conditions permit.
- Valet parking for L Tower residents continues on the north side of The Esplanade, west of Scott Street.
LOOKING AHEAD:
- The Large Crane Tower is currently scheduled to remain in place over the winter and will be removed in March, 2015.
- The Sony Centre Plaza is scheduled to be completed in the first quarter of 2015 and be ready for a spring opening.