Backstage Construction Schedule January 17 – 23, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 17 – 23, 2015.  

Note: 34th Floor is scheduled to be poured this week. However, depending on the severity of the weather, concrete pours noted here may be cancelled and rescheduled. Please check back for regular updates. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-17-23-2015

Backstage - Straight Up from The Esplanade, January 16, 2015

Backstage – Straight Up from The Esplanade, January 16, 2015

Saturday, January 17, 2015

  • Using concrete pump to pour L Tower Parking pedestrian tunnel floor, starting at 10:30am. There will be no impact to traffic.

Monday, January 19, 2015

  • Rebar delivery, scheduled to begin at 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm

Tuesday, January 20, 2015

  • 34th Floor slab concrete pours #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Wednesday, January 21, 2015

  • 34th Floor slab concrete pours #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Thursday, January 22, 2015

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 34th Floor slab concrete pours #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (45 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Friday, January 23, 2015

  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.
Backstage Looking Up - January 16, 2015

Backstage Looking Up – January 16, 2015

 NOTES:

    • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: