Backstage Construction Schedule January 17 – 23, 2015
January 16, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 17 – 23, 2015.
Note: 34th Floor is scheduled to be poured this week. However, depending on the severity of the weather, concrete pours noted here may be cancelled and rescheduled. Please check back for regular updates.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-17-23-2015
Saturday, January 17, 2015
- Using concrete pump to pour L Tower Parking pedestrian tunnel floor, starting at 10:30am. There will be no impact to traffic.
Monday, January 19, 2015
- Rebar delivery, scheduled to begin at 7:00 am.
- A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm
Tuesday, January 20, 2015
- 34th Floor slab concrete pours #1, by subcontractor Italform, scheduled to begin at 10:30 am.
- After slab, wall & column pour (33 metres of concrete).
- Concrete Finishing until to 11:00 pm.
Wednesday, January 21, 2015
- 34th Floor slab concrete pours #2, by subcontractor Italform, scheduled to begin at 10:30 am.
- After slab, wall & column pour (33 metres of concrete).
- Concrete Finishing until to 11:00 pm.
Thursday, January 22, 2015
- Rebar delivery, scheduled to begin at 7:00 am.
- 34th Floor slab concrete pours #3, by subcontractor Italform, scheduled to begin at 10:30 am.
- After slab, wall & column pour (45 metres of concrete).
- Concrete Finishing until to 11:00 pm.
Friday, January 23, 2015
- A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.