Backstage Construction Schedule January 10 – 16, 2015
January 15, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 10 – 16, 2015. Note: All concrete pours from last week have been rescheduled to this week due to last week’s severe weather.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-10-16-2015
Saturday, January 10, 2015
- Three tractor trail loads of windows will be delivered, starting at 9:00 am.
- The south curb lane of The Esplanade will be occupied during delivery times.
Monday, January 12, 2015
- 33rdFloor slab concrete pours #1 + #2, by subcontractor Italform, scheduled to begin at 8:00 am.
- Concrete Finishing until to 11:30 pm.
Tuesday, January 13, 2015
- Rebar delivery, scheduled to begin at 7:00 am.
- CANCELLED – A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm
Wednesday, January 14, 2015
- 33rdFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
- After slab, wall & column pour (33 metres of concrete).
- Concrete Finishing until to 11:00 pm.
Thursday, January 15, 2015
- CANCELLED – Rebar delivery, scheduled to begin at 7:00 am.
- A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.
Friday, January 16, 2015
- A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.