Backstage Construction Schedule January 10 – 16, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 10 – 16, 2015.  Note: All concrete pours from last week have been rescheduled to this week due to last week’s severe weather. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-10-16-2015

Dominion Building from Backstage Condo

Dominion Building from Backstage Condo

 

Saturday, January 10, 2015

  • Three tractor trail loads of windows will be delivered, starting at 9:00 am.
  • The south curb lane of The Esplanade will be occupied during delivery times.

Monday, January 12, 2015

  • 33rdFloor slab concrete pours #1 + #2, by subcontractor Italform, scheduled to begin at 8:00 am.
  • Concrete Finishing until to 11:30 pm.

Tuesday, January 13, 2015

  • Rebar delivery, scheduled to begin at 7:00 am.
  • CANCELLED – A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm

Wednesday, January 14, 2015

  • 33rdFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Thursday, January 15, 2015

  • CANCELLED – Rebar delivery, scheduled to begin at 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.

Friday, January 16, 2015

  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.
Concrete Truck pulling into Backstage

Concrete Truck pulling into Backstage

 NOTES:

    • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: