L Tower Update January 12 – 16, 2015
January 12, 2015 Leave a comment
- 8 The Esplanade – L Tower Saturday, Monday, January 12, 2015 – Friday, January 16
Sidewalk work has been postponed until weather conditions improve.
Interior work on the site is ongoing. As the L Tower is partially occupied, there will be people coming and going to their homes and the valet parking service for L Tower residents will be ongoing.
- Interior work continues on multiple floors.
- Move-ins are ongoing through the Yonge Street entrance.
- Sidewalk work has been postponed till weather conditions improve.
- The Large Crane Tower is currently scheduled to remain in place over the winter and will be removed in March, 2015.
- The Sony Centre Plaza is scheduled to be completed in the first quarter of 2015 and be ready for a spring opening.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-10-16-2015