Backstage Construction Schedule January 5 – 9, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 5 – 9, 2015.  

Note: Due to severe weather all concrete pours were cancelled this week.

View from Backstge to the Dominon Building and the Royal York

View from Backstage to the Dominion Building and the Royal York

 

Monday, January 5, 2015

  • Concrete pours cancelled. 

Tuesday, January 6, 2015

  • Concrete pours cancelled. 

Wednesday, January 7, 2015

  • Concrete pours cancelled. 

Thursday, January 8, 2015

  • Tentative – Rebar delivery, scheduled to begin at 7:00 am.
  • Concrete pours cancelled. 

 

Friday, January 9, 2015

  • Concrete pours cancelled. 

 NOTES:

  • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: