Backstage Construction Schedule January 31 – February 6, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 31 – February 6, 2015.  

Note: Concrete for the 36th Floor slab is scheduled to begin Wednesday, February 4. However, depending on the severity of the weather, concrete pours noted here may be cancelled and rescheduled. Please check back for regular updates. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-31-Feb-6-2015

The Railway Corridor south from Backstage

The Railway Corridor south from Backstage

Saturday, January 31, 2015

  • Raising the tower crane three floors, starting at 9:00am.

Monday, February 2

  • Rebar delivery starting at 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (53 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, February 3

  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, February 4

  • 36th Floor slab concrete pours #1, by subcontractor Italform, scheduled to begin at 11:o0 am.
  • After slab, wall & column pour (40 metres of concrete). 
  • Concrete Finishing until to 11:30 pm.

ThursdayFebruary 5

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 36th Floor slab concrete pours #2, by subcontractor Italform, scheduled to begin at 11:00 am.
  • After slab, wall & column pour (53 metres of concrete). 
  • Concrete Finishing until to 11:30 pm.

Friday, February 6

  • 36th Floor slab concrete pours #3, by subcontractor Italform, scheduled to begin at 11:00 am.
  • After slab, wall & column pour (50 metres of concrete). 
  • Concrete Finishing until to 11:30 pm.
Interior PATH space at Backstage

Interior PATH space at Backstage

 NOTES:

    • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower Update January 31 – February 6, 2015

8 The Esplanade – L Tower Saturday, Saturday, January 31, 2015 – Friday, February 6

New neighbourhood residents are occupying their as move-ins continue to the L Tower. Streetscape improvements continue as weather permits.

L Tower and Backstage

L Tower and Backstage

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-31-Feb-6-2015

  • Interior work continues on multiple floors.
  • Move-ins are ongoing through the Yonge Street entrance.
  • Sidewalk work will continue as weather conditions permit.
  • Valet parking for L Tower residents continues on the north side of The Esplanade, west of Scott Street.
NW view of the Financial District from L Tower

NW view of the Financial District from L Tower

LOOKING AHEAD: 

  • The Large Crane Tower is currently scheduled to remain in place over the winter and will be removed in March, 2015.
  • The Sony Centre Plaza is scheduled to be completed in the first quarter of 2015 and be ready for a spring opening.

Backstage Construction Schedule January 24 – 30, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 24 – 30, 2015.  

Note: 35th Floor is scheduled to be poured this week. However, depending on the severity of the weather, concrete pours noted here may be cancelled and rescheduled. Please check back for regular updates. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-24-30-2015

Backstage Concrete Truck

Backstage Concrete Truck

Saturday, January 24, 2015

  • Window delivery–2 floors worth of exterior windows, starting at 9:00 am. There may be some impact on eastbound traffic.

Monday, January 26, 2015

  • No rebar deliveries or concrete pours scheduled. 

Tuesday, January 27, 2015

  • 35th Floor slab concrete pours #1, by subcontractor Italform, scheduled to begin at 11:00 am.
  • After slab, wall & column pour (50 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Wednesday, January 28, 2015

  • 35th Floor slab concrete pours #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (40 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Thursday, January 29, 2015

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 35th Floor slab concrete pours #3, by subcontractor Italform, scheduled to begin at 11:00 am.
  • After slab, wall & column pour (53 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Friday, January 23, 2015

  • A wall and column concrete pour, by subcontractor Italform (63 metres of concrete), scheduled to run from 12:30 pm.
Backstage Black and White Construction Site

Backstage Black and White Construction Site

 NOTES:

    • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower Update January 24 – 30, 2015

8 The Esplanade – L Tower Saturday, Saturday, January 24, 2015 – Friday, January 30 

New neighbourhood residents are occupying their as move-ins continue to the L Tower. Streetscape improvements continue as weather permits.

Looking east along The Esplanade from L Tower

Looking east along The Esplanade from L Tower

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-24-30-2015

  • Interior work continues on multiple floors.
  • Move-ins are ongoing through the Yonge Street entrance.
  • Sidewalk work will continue as weather conditions permit.
  • Valet parking for L Tower residents continues on the north side of The Esplanade, west of Scott Street.
L Tower (detail) Yonge & The Esplanade

L Tower (detail) Yonge & The Esplanade

LOOKING AHEAD: 

  • The Large Crane Tower is currently scheduled to remain in place over the winter and will be removed in March, 2015.
  • The Sony Centre Plaza is scheduled to be completed in the first quarter of 2015 and be ready for a spring opening.

Backstage Construction Schedule January 17 – 23, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 17 – 23, 2015.  

Note: 34th Floor is scheduled to be poured this week. However, depending on the severity of the weather, concrete pours noted here may be cancelled and rescheduled. Please check back for regular updates. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-17-23-2015

Backstage - Straight Up from The Esplanade, January 16, 2015

Backstage – Straight Up from The Esplanade, January 16, 2015

Saturday, January 17, 2015

  • Using concrete pump to pour L Tower Parking pedestrian tunnel floor, starting at 10:30am. There will be no impact to traffic.

Monday, January 19, 2015

  • Rebar delivery, scheduled to begin at 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm

Tuesday, January 20, 2015

  • 34th Floor slab concrete pours #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Wednesday, January 21, 2015

  • 34th Floor slab concrete pours #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Thursday, January 22, 2015

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 34th Floor slab concrete pours #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (45 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Friday, January 23, 2015

  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.
Backstage Looking Up - January 16, 2015

Backstage Looking Up – January 16, 2015

 NOTES:

    • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower Update January 17 – 23, 2015

8 The Esplanade – L Tower Saturday, Saturday, January 17, 2015 – Friday, January 23 

As the L Tower is partially occupied, there will be people coming and going to their homes and the valet parking service for L Tower residents will be ongoing.

Installing exterior glazing at L Tower, January 16, 2015

Installing exterior glazing at L Tower, January 16, 2015

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-17-23-2015

  • Exterior glazing installation.
  • Interior work continues on multiple floors.
  • Move-ins are ongoing through the Yonge Street entrance.
  • Sidewalk work has been postponed till weather conditions improve.
Working in the cold at L Tower, January 16, 2015

Working in the cold at L Tower, January 16, 2015

LOOKING AHEAD: 

  • The Large Crane Tower is currently scheduled to remain in place over the winter and will be removed in March, 2015.
  • The Sony Centre Plaza is scheduled to be completed in the first quarter of 2015 and be ready for a spring opening.

Backstage Construction Schedule January 10 – 16, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 10 – 16, 2015.  Note: All concrete pours from last week have been rescheduled to this week due to last week’s severe weather. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-10-16-2015

Dominion Building from Backstage Condo

Dominion Building from Backstage Condo

 

Saturday, January 10, 2015

  • Three tractor trail loads of windows will be delivered, starting at 9:00 am.
  • The south curb lane of The Esplanade will be occupied during delivery times.

Monday, January 12, 2015

  • 33rdFloor slab concrete pours #1 + #2, by subcontractor Italform, scheduled to begin at 8:00 am.
  • Concrete Finishing until to 11:30 pm.

Tuesday, January 13, 2015

  • Rebar delivery, scheduled to begin at 7:00 am.
  • CANCELLED – A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm

Wednesday, January 14, 2015

  • 33rdFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Thursday, January 15, 2015

  • CANCELLED – Rebar delivery, scheduled to begin at 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.

Friday, January 16, 2015

  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.
Concrete Truck pulling into Backstage

Concrete Truck pulling into Backstage

 NOTES:

    • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower Update January 12 – 16, 2015

  • 8 The Esplanade – L Tower Saturday, Monday, January 12, 2015 – Friday, January 16 

Sidewalk work has been postponed until weather conditions improve. 

Interior work on the site is ongoing. As the L Tower is partially occupied, there will be people coming and going to their homes and the valet parking service for L Tower residents will be ongoing.

L Tower from Yonge Street, looking south east

L Tower from Yonge Street, looking south east

  • Interior work continues on multiple floors.
  • Move-ins are ongoing through the Yonge Street entrance.
  • Sidewalk work has been postponed till weather conditions improve.
  • The Large Crane Tower is currently scheduled to remain in place over the winter and will be removed in March, 2015.  
  • The Sony Centre Plaza is scheduled to be completed in the first quarter of 2015 and be ready for a spring opening.

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-10-16-2015

Backstage Construction Schedule January 5 – 9, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 5 – 9, 2015.  

Note: Due to severe weather all concrete pours were cancelled this week.

View from Backstge to the Dominon Building and the Royal York

View from Backstage to the Dominion Building and the Royal York

 

Monday, January 5, 2015

  • Concrete pours cancelled. 

Tuesday, January 6, 2015

  • Concrete pours cancelled. 

Wednesday, January 7, 2015

  • Concrete pours cancelled. 

Thursday, January 8, 2015

  • Tentative – Rebar delivery, scheduled to begin at 7:00 am.
  • Concrete pours cancelled. 

 

Friday, January 9, 2015

  • Concrete pours cancelled. 

 NOTES:

  • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

L Tower Update January 5 – 10, 2015

8 The Esplanade – L Tower Saturday, Monday, January 5, 2015 – Saturday, January 10 

Due to severe weather sidewalk work was curtailed this week. 

Interior work on the site is ongoing. As the L Tower is partially occupied, there will be people coming and going to their homes and the valet parking service for L Tower residents will be ongoing.

 

L Tower on The Esplanade looking west.

L Tower on The Esplanade looking west.

  • Interior work continues on multiple floors.
  • Move-ins are ongoing through the Yonge Street entrance.
  • Sidewalk work on Yonge Street is ongoing, weather permitting. The revised update is that sidewalk work will be completed in January at the corner of The Esplanade and Yonge.
  • The Large Crane Tower is currently scheduled to remain in place over the winter and will be removed in March, 2015.  
  • The Sony Centre Plaza is scheduled to be completed in the first quarter of 2015 and be ready for a spring opening.