Backstage Construction Schedule December 29 – January 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for December 29, 2014 – January 3, 2015. The next schedule will be published by Monday, January 5.

NOTE: Concrete pours resume on January 5, 2015. 

Happy New Year!

Backstage 4th floor looking west

Backstage 4th floor looking west

Monday, December 29

  • Interior work on-site.
  • Housekeeping work on-site.

Tuesday, December 30

  • Interior work on-site.
  • Housekeeping work on-site.

Wednesday, December 31

  • Interior work. Site closing early. 

Thursday, January 1 – Site Closed for the Holiday. 

Friday, January 2

  • Internal work on site from 9:00 am.

Saturday, January 3 

  • Internal work on site from 9:00 am.
Backstage 4th Floor Looking Southwest

Backstage 4th Floor Looking Southwest

 NOTES:

  • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: