Backstage Construction Schedule December 29 – January 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for December 29, 2014 – January 3, 2015. The next schedule will be published by Monday, January 5.

NOTE: Concrete pours resume on January 5, 2015. 

Happy New Year!

Backstage 4th floor looking west

Backstage 4th floor looking west

Monday, December 29

  • Interior work on-site.
  • Housekeeping work on-site.

Tuesday, December 30

  • Interior work on-site.
  • Housekeeping work on-site.

Wednesday, December 31

  • Interior work. Site closing early. 

Thursday, January 1 – Site Closed for the Holiday. 

Friday, January 2

  • Internal work on site from 9:00 am.

Saturday, January 3 

  • Internal work on site from 9:00 am.
Backstage 4th Floor Looking Southwest

Backstage 4th Floor Looking Southwest

 NOTES:

  • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

L Tower Update December 29 – January 3

8 The Esplanade – L Tower Saturday, December 29, 2014 – Saturday, January 3, 2015

Happy New Year!

Work on the site will not occur during the statutory  holidays. However, as the L Tower is now partially occupied, there will be people coming and going to their homes and the valet parking service for L Tower residents will be ongoing.

 

L Tower, The Esplanade, December 29, 2014

L Tower, The Esplanade, December 29, 2014

  • Interior work continues on multiple floors.
  • Move-ins are ongoing through the Yonge Street entrance.
  • Sidewalk work on Yonge Street is ongoing, weather permitting. The revised update is that sidewalk work will be completed in January at the corner of The Esplanade and Yonge.
  • The Large Crane Tower is currently scheduled to remain in place over the winter and will be removed in March, 2015.  
  • The Sony Centre Plaza is scheduled to be completed in the first quarter of 2015 and be ready for a spring opening.
L Tower from St. James Park December 29

L Tower from St. James Park December 29

Backstage Construction Schedule December 20 – 27 – Happy Holidays

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for December 20 – 27, 2014. The next schedule will be published on Monday, December 29. Updates are published when required. 

Happy Holidays!

Backstage Looking Up from Yonge & The Esplanade, December 19, 2014

Backstage Looking Up from Yonge & The Esplanade, December 19, 2014

Saturday, December 20.

  • Window delivery 4 tractor trailers which will occupy the south lane of The Esplanade, from 9:00 am 1:00 pm

Monday, December 22

  • Rebar delivery, scheduled to begin at 7:00 am.
  • Cancelled — 33rd Floor slab concrete pour, by subcontractor Italform, scheduled to begin at 11:00 am.
  • Cancelled — After slab, wall & column concrete pour (45 metres of concrete). 
  • Cancelled — Concrete Finishing until to 11:00 pm.

Tuesday, December 23

  • Cancelled — A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, December 24 

  • Interior work throughout the day.

ThursdayDecember 25 – Christmas Day – Site Closed for the Holiday. 

Friday, December 26 – Boxing Day – Site Closed for the Holiday. 

Saturday, December 27 

  • Internal work on site from 9:00 am.
Backstage at 32 floors, December 19, 2014

Backstage at 32 floors, December 19, 2014

 NOTES:

  • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule December 13 – 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for December 13 – 19, 2014.

Backstage crash wall adjacent the rail corridor

Backstage crash wall adjacent the rail corridor

Saturday, December 13

  • Raising the tower crane, from 9:00 am.
  • Window delivery which will occupy the south lane of The Esplanade, from 11:00 am.

Monday, December 15

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 31stFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 11:00 am.
  • After slab, wall & column concrete pour (45 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Tuesday, December 16

  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, December 17

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 32ndFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 11:30 am.
  • After slab, wall & column pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

ThursdayDecember 18

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 32ndFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 11:00 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 11:00 pm.

Friday, December 19

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 32nd Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 11:00 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 11:00 pm.
Future Public Exhibit Space on the 2nd floor of Backstage

Future Public Exhibit Space on the 2nd floor of Backstage

 NOTES:

  • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

L Tower Update December 13 – 19

8 The Esplanade – L Tower Saturday, December 13 – Friday, December 19

  • Interior work continues on multiple floors.
  • Move-ins are ongoing through the Yonge Street entrance.
  • Sidewalk work on Yonge Street is ongoing, weather permitting and should be completed within the coming weeks. Sidewalk work at the entrance to the L Tower at the corner of Yonge is also progressing. More easterly sidewalk work on the north side The Esplanade, on the south edge of the Sony Centre, will not proceed until the tower crane is disassembled and removed. 
L Tower, Backstage & 25 The Esplanade

L Tower, Backstage & 25 The Esplanade

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Dec 13-19-2014

NOTE: We’ll be providing ongoing updates and approximate timelines on the crane, and more on The Esplanade sidewalk build out in the coming weeks. 

Backstage Construction Schedule December 6 – 12

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for December 6 – 12, 2014.

Backstage, L Tower, 25 The Esplanade, December 5

Backstage, L Tower, 25 The Esplanade, December 5

Saturday, December 6

  • Dominus construction crew doing winter protection work on-site, from 9:00 am.
  • Interior suite work from 9:00 am.
Loading Concrete at Backstage December 5

Loading Concrete at Backstage December 5

Monday, December 8

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 30thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 11:00 am.
  • After slab, wall & column concrete pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Tuesday, December 9

  • 30thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 11:30 am.
  • After slab, wall & column pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Wednesday, December 10

  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.

ThursdayDecember 11

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 31stFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 11:00 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 11:00 pm.

Friday, December 12

  • 31st Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 11:00 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 11:00 pm.
Backstage Black & White

Backstage Black & White

 NOTES:

  • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

L Tower Update December 6 – 12

8 The Esplanade – L Tower – UPDATE

Saturday, December 6 – Friday, December 12

  • Interior work continues on multiple floors.
  • Move-ins are ongoing through the Yonge Street entrance.
  • Sidewalk work on Yonge Street is ongoing and should be completed within the next 2 weeks.
L Tower Crane in use Dec 5

L Tower Crane in use December 5

 

Sidewalks on The Esplanade at Yonge Street are progressing. 

L Tower Sidewalk work Yonge & The Esplanade

L Tower sidewalk work Yonge & The Esplanade

 

L Tower Sidewalk work on The Esplanade

L Tower sidewalk work on The Esplanade

 

NOTE: We’ll be providing ongoing updates and approximate timelines on the crane, and more on The Esplanade sidewalk build out in the coming weeks. 