8 The Esplanade – L Tower – UPDATE – November 28 – December 5, 2014

Saturday, November 29 – December 5

  • Interior work continues on multiple floors.
  • Move-ins are ongoing through the Yonge Street entrance.
  • Sidewalk wok on Yonge Street is ongoing and should be completed within the next 2 weeks.

Sidewalks on Yonge Street are progressing. 

L TOWER sidewalk 2

Section of finished sidewalk at the L Tower on Yonge Street.

L TOWER sidewalk 1

Section of unfinished sidewalk at the L Tower on Yonge Street.

 

The L Tower Parking Garage located underneath 1 The Esplanade (Backstage) has been operating on a valet parking basis with approximately 30 new L Tower resident vehicles using the space and counting. 

L Tower Parking entrance

L Tower Parking Garage entrance (Valet Service while construction continues at 1 The Esplanade)

 

L Tower Parking ramp

L Tower Parking Ramp

 

L Tower Parking P1

L Tower Parking Level P1

NOTE: We’ll be providing further updates and approximate timelines on the crane, and The Esplanade sidewalk next week. 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: