Backstage Construction Schedule November 29 – December 5

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 29 – December 5, 2014.

L Tower, 25 The Esplanade, Backstage as seen from the GO Bus Terminal.

L Tower, 25 The Esplanade, Backstage as seen from the GO Bus Terminal.

Saturday, November 29

  • Dominus construction crew doing housekeeping work on-site, from 9:00 am.
  • Electrical and plumbing subcontractors working in the building from 9:00 am.
Exterior Yonge Street Rail Bridge - Future PATH connection section

Exterior connection to the Yonge Street Rail Bridge looking west. Future PATH connection.

Monday, December 1

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 29thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall concrete pour (33 metres of concrete). 
  • Concrete Finishing until to 10:30 pm.

Tuesday, December 2

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 29thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall concrete pour (33 metres of concrete). 
  • Concrete Finishing until to 10:30 pm.

Wednesday, December 3

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

ThursdayDecember 4

  • 30thFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Friday, December 5

  • 30th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.
Interior 2nd floor Backstage East PATH section

Interior 2nd floor, looking east along the southern half of the future Backstage East PATH section and additional exhibit space. When finished this space will be 2x wider.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: