Backstage Construction Schedule November 29 – December 5
November 28, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 29 – December 5, 2014.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-November-29-Dec 5-2014
Saturday, November 29
- Dominus construction crew doing housekeeping work on-site, from 9:00 am.
- Electrical and plumbing subcontractors working in the building from 9:00 am.
Monday, December 1
- Rebar delivery, scheduled to begin at 7:00 am.
- 29thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
- After slab, wall concrete pour (33 metres of concrete).
- Concrete Finishing until to 10:30 pm.
Tuesday, December 2
- Rebar delivery, scheduled to begin at 7:00 am.
- 29thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
- After slab, wall concrete pour (33 metres of concrete).
- Concrete Finishing until to 10:30 pm.
Wednesday, December 3
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Thursday, December 4
- 30thFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Friday, December 5
- 30th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.

Interior 2nd floor, looking east along the southern half of the future Backstage East PATH section and additional exhibit space. When finished this space will be 2x wider.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.