Backstage Construction Schedule November 22 – 28
November 24, 2014 Leave a comment
UPDATED November 25–This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 22 – 28, 2014.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-November-22-28-2014
Saturday, November 22
- Subcontractor, Italform doing high elevation rescue training off the crane.
Please Note: During the training a dummy will be dropped and “rescued.”
- Dominus construction crew doing housekeeping work on-site, from 9:00 am.
- Electrical and plumbing subcontractors working in the building from 9:00 am.
Monday, November 24
- CANCELLED – 28thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
- After slab, wall concrete pour (45 metres of concrete).
- Concrete Finishing until to 10:30 pm.
Tuesday, November 25
- Rebar delivery, scheduled to begin at 7:00 am.
- Rescheduled from Monday: 28thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
- After slab, wall concrete pour (45 metres of concrete).
- Concrete Finishing until to 10:30 pm.
Wednesday, November 26
- 28th Floor slab concrete pour 3, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Thursday, November 27
- Rebar delivery from 7:00 am.
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Friday, November 28
- 29th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.