Backstage Construction Schedule November 17 – 21
November 17, 2014 Leave a comment
UPDATED – November 19
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 17 – 21, 2014.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-November-17-21-2014
- Please click here for general information on concrete pours.
Monday, November 17
- The Esplanade will be closed during the day to eastbound vehicle traffic by contractor Distinct Tech. They will be installing conduits for fibre-optic cable for Beanfield Metroconnect.
- Please note: Beanfield Metroconnect schedules their own work and is responsible for relevant permits and did not advise on-site construction managers of the scheduling of this work prior to late Friday, November 14.
- CANCELLED – 27thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
- Cancelled – Concrete Finishing until to 10:30 pm.
Tuesday, November 18
- Rebar delivery, scheduled to begin at 7:00 am.
- CANCELLED – A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Wednesday, November 19
- 27th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour till 8:30 pm.
- Concrete Finishing until to 10:30 pm.
Thursday, November 20
- Rebar delivery from 7:00 am.
- 28thFloor slab concrete pour 1, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Friday, November 21
- 28th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.