Backstage Construction Schedule November 8 – 14

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for November 8 – 14, 2014.

Please note: there will be a road closure of The Esplanade from Yonge Street to Scott Street from 9:00 am to 7:00 pm Monday, November 10 and Tuesday November 12. A copy of the ROAD CLOSURE PERMIT for November 10 – 11 is provided here: SBACKSTAGE 14110715270. Pedestrian access will be provided, as safety permits, on the north side The Esplanade adjacent the L Tower. 

The crane at Backstage seen from the 36th floor of the L Tower

The crane at Backstage seen from the 36th floor of the L Tower

Saturday, November 8

  • Subcontractor, Italform doing high elevation rescue training off the crane.
  • Dominus construction crew doing housekeeping work on-site, from 9:00 am. 
  • Electrical and plumbing subcontractors working in the building from 9:00 am.

Monday, November 10

  • Rebar delivery from 7:00 am.
  • ROAD CLOSURE OF THE ESPLANADE – 9:00 am – 7:00 pm to permit relocation of the hoardings and concrete barriers.
  • Pedestrians will be permitted access to Yonge Street on the north side of The Esplanade adjacent to the L Tower.
  • 2 Paid Duty Police Officers will be on site.
  • Please click on the link to the right to view or download the Road Closure Permit: SBACKSTAGE 14110715270
  • 26thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Tuesday, November 11

  • ROAD CLOSURE OF THE ESPLANADE – 9:00 am – 7:00 pm to permit relocation of the hoardings and concrete barriers.
  • Pedestrians will be permitted access to Yonge Street on the north side of The Esplanade adjacent to the L Tower.
  • 2 Paid Duty Police Officers will be on site.
  • Please click on the link to the right to view or download the Road Closure Permit: SBACKSTAGE 14110715270
  • 26thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Wednesday, November 12

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

ThursdayNovember 13

  • Rebar delivery from 7:00 am.
  • 27thFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Friday, November 14

  • 27th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: