Backstage Construction Schedule November 29 – December 5

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 29 – December 5, 2014.

L Tower, 25 The Esplanade, Backstage as seen from the GO Bus Terminal.

L Tower, 25 The Esplanade, Backstage as seen from the GO Bus Terminal.

Saturday, November 29

  • Dominus construction crew doing housekeeping work on-site, from 9:00 am.
  • Electrical and plumbing subcontractors working in the building from 9:00 am.
Exterior Yonge Street Rail Bridge - Future PATH connection section

Exterior connection to the Yonge Street Rail Bridge looking west. Future PATH connection.

Monday, December 1

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 29thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall concrete pour (33 metres of concrete). 
  • Concrete Finishing until to 10:30 pm.

Tuesday, December 2

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 29thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall concrete pour (33 metres of concrete). 
  • Concrete Finishing until to 10:30 pm.

Wednesday, December 3

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

ThursdayDecember 4

  • 30thFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Friday, December 5

  • 30th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.
Interior 2nd floor Backstage East PATH section

Interior 2nd floor, looking east along the southern half of the future Backstage East PATH section and additional exhibit space. When finished this space will be 2x wider.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

L Tower Update November 28 – December 5

8 The Esplanade – L Tower – UPDATE – November 28 – December 5, 2014

Saturday, November 29 – December 5

  • Interior work continues on multiple floors.
  • Move-ins are ongoing through the Yonge Street entrance.
  • Sidewalk wok on Yonge Street is ongoing and should be completed within the next 2 weeks.

Sidewalks on Yonge Street are progressing. 

L TOWER sidewalk 2

Section of finished sidewalk at the L Tower on Yonge Street.

L TOWER sidewalk 1

Section of unfinished sidewalk at the L Tower on Yonge Street.

 

The L Tower Parking Garage located underneath 1 The Esplanade (Backstage) has been operating on a valet parking basis with approximately 30 new L Tower resident vehicles using the space and counting. 

L Tower Parking entrance

L Tower Parking Garage entrance (Valet Service while construction continues at 1 The Esplanade)

 

L Tower Parking ramp

L Tower Parking Ramp

 

L Tower Parking P1

L Tower Parking Level P1

NOTE: We’ll be providing further updates and approximate timelines on the crane, and The Esplanade sidewalk next week. 

Backstage Construction Schedule November 22 – 28

UPDATED November 25–This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 22 – 28, 2014.

Backstage, south west corner, November 21, 2014

Backstage, south west corner, November 21, 2014

Saturday, November 22

  • Subcontractor, Italform doing high elevation rescue training off the crane.
    Please Note: During the training a dummy will be dropped and “rescued.”
  • Dominus construction crew doing housekeeping work on-site, from 9:00 am. 
  • Electrical and plumbing subcontractors working in the building from 9:00 am.

Monday, November 24

  • CANCELLED – 28thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall concrete pour (45 metres of concrete). 
  • Concrete Finishing until to 10:30 pm.

Tuesday, November 25

  • Rebar delivery, scheduled to begin at 7:00 am.
  • Rescheduled from Monday: 28thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall concrete pour (45 metres of concrete). 
  • Concrete Finishing until to 10:30 pm.

Wednesday, November 26

  • 28th Floor slab concrete pour 3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

ThursdayNovember 27

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Friday, November 28

  • 29th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule November 17 – 21

UPDATED – November 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 17 – 21, 2014.

Backstage parking entrance interior

Backstage parking entrance interior

Monday, November 17

  • The Esplanade will be closed during the day to eastbound vehicle traffic by contractor Distinct Tech. They will be installing conduits for fibre-optic cable for Beanfield Metroconnect.
    • Please note: Beanfield Metroconnect schedules their own work and is responsible for relevant permits and did not advise on-site construction managers of the scheduling of this work prior to late Friday, November 14. 
  • CANCELLED – 27thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • Cancelled – Concrete Finishing until to 10:30 pm.

Tuesday, November 18

  • Rebar delivery, scheduled to begin at 7:00 am.
  • CANCELLED – A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, November 19

  • 27th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour till 8:30 pm.
  • Concrete Finishing until to 10:30 pm.

ThursdayNovember 20

  • Rebar delivery from 7:00 am.
  • 28thFloor slab concrete pour 1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Friday, November 21

  • 28th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

New: Esplanade reopened early Nov 15. Daytime closure Nov 17

UPDATEThe Esplanade at Yonge reopened to vehicular traffic after lunch on November 15 and will remain open all weekend. A daytime road closure is expected Monday November 17 for fibre-optic cable work (please see below for details). 

Esplanade reopened to car traffic, November 15

The eastbound lane of The Esplanade at Yonge, reopened to car traffic earlier than expected today, November 15.

Saturday, November 15

  • The eastbound vehicle lane, which has been closed from Monday November 10 – Friday November 14, has been repaved and opened earlier than expected, in the early afternoon.
  • Housekeeping activities will be occurring through the day at Backstage.
  • Interior work and movie-ins (from Yonge Street) will be occurring at L Tower through the day.

Sunday, November 16

  • The eastbound vehicle lane will be open all day Sunday.

Monday, November 17

  • The Esplanade will be closed during the day to eastbound vehicle traffic by contractor Distinct Tech. They will be installing conduits for fibre-optic cable for Beanfield Metroconnect.
  • Please note: Beanfield Metroconnect schedules their own work and is responsible for relevant permits and did not advise on-site construction managers of the scheduling of this work prior to late Friday, November 14. 
The eastbound lane of The Esplanade reopened earlier than expected today - November 15.

The eastbound lane of The Esplanade reopened earlier than expected today – November 15.

The construction management team apologies for any inconvenience caused by the closure of the eastbound vehicle lane between Yonge and Scott. 

Esplanade Repaving November 15 + Vehicular closure November 17

Please note that eastbound vehicle lane of The Esplanade between Yonge and Scott, will be repaved on Saturday and should reopen to vehicular traffic on Sunday, November 16 (or possibly as early as late Saturday). We have also been advised that The Esplanade will be closed again to vehicle traffic on Monday, November 17 to facilitate fibre-optic cable installation by Beanfield Metroconnect. Details below: 

Area of the Esplanade to be repaved Saturday Nov 15/14

Area of the Esplanade to be repaved Saturday Nov 15/14

Saturday, November 15

  • The eastbound vehicle lane, which has been closed from Monday November 10 – Friday November 14, will be repaved, starting at 9:00 am.
  • Housekeeping activities will be occurring through the day at Backstage.
  • Interior work and movie-ins (from Yonge Street) will be occurring at L Tower through the day.

Sunday, November 16

  • It is expected that the eastbound vehicle lane will be reopened for Sunday, if not by late Saturday.

Monday, November 17

  • The Esplanade will be closed during the day to eastbound vehicle traffic by contractor Distinct Tech. They will be installing conduits for fibre-optic cable for Beanfield Metroconnect.
  • Please note: Beanfield Metroconnect schedules their own work and is responsible for relevant permits and did not advise on-site construction managers of the scheduling of this work prior to late Friday, November 14. 

* * * 

The construction management team apologies for any inconvenience caused by the closure of the eastbound vehicle lane between Yonge and Scott. 

Update on Esplanade vehicular closure November 15 – 17

Please note that The Esplanade will remain closed to vehicular traffic through the weekend of November 15 – 17.

Saturday, November 15

  • The eastbound vehicle lane, which has been closed from Monday November 10 – Friday November 14, will be repaved, starting at 9:00 am.
  • Housekeeping activities will be occurring through the day at Backstage.
  • Interior work and movie-ins (from Yonge Street) will be occurring at L Tower through the day.

Sunday, November 16

  • It is expected that the eastbound vehicle lane will be reopened for Sunday, if not by late Saturday.

Monday, November 17

  • The Esplanade will be closed during the day to eastbound vehicle traffic by contractor Distinct Tech. They will be installing conduits for fibre-optic cable for Beanfield Metroconnect.
  • Please note: Beanfield Metroconnect schedules their own work and is responsible for relevant permits and did not advise on-site construction managers of the scheduling of this work prior to late Friday, November 14. 

 

Area of the Esplanade to be repaved Saturday Nov 15/14

Area of the Esplanade to be repaved Saturday Nov 15/14

The construction management team apologies for any inconvenience caused by the closure of the eastbound vehicle lane between Yonge and Scott. 

Update on Esplanade vehicular closure November 12

Please note that The Esplanade will remain closed to vehicular traffic through the weekend of November 15/16.

The roadway requires resurfacing. Our present information is that a contractor is not available to do the repaving work until Saturday November 15 and it will take at least a day for the new asphalt to cure. 

Pedestrian access is being maintained both on the south side of the street beside the Backstage condominium construction site, and on the north side to permit access to the L Tower. 

The construction management team apologies for any inconvenience this may cause. 

The section of The Esplanade that requires resurfacing.

The section of The Esplanade that requires resurfacing.

Update on Esplanade vehicular closure November 11

Please note that The Esplanade will remain closed to vehicular traffic until the road is resurfaced to make it safe to drive on. Pedestrian access is being maintained both on the south side of the street beside the Backstage condominium construction site, as well as access on the north side to the L Tower. Every effort is being made to get the road resurfaced ASAP and re-opened to eastbound car traffic.

The Esplanade closed to cars between Yonge and Scott

The Esplanade closed to cars between Yonge and Scott

Update Esplanade Road Closure Nov 10

image

The Esplanade 5 pm November 10

Please note that due to the unexpected condition of the road bed, vehicular traffic between Yonge Street and Scott Street will remain closed overnight. Updates will be provided on November 11.