This is the current construction schedule for 8 The Esplanade – L Tower  October 25 – 31, 2014

NOTE: New residents are continuing to move into the L Tower When moves occur they are loading in on Yonge Street. As external construction comes closer to completion, the dimensions of the future sidewalk area on the north side of The Esplanade is beginning to emerge.  

Saturday, October 25

  • Interior work on site.
  • Move-ins through the Yonge Street entrance.

Monday, October 27

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Tuesday, October 28

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Wednesday, October 29

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Thursday, October 30

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Friday, October 31

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: