Backstage Construction Schedule October 25 – 31
October 24, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for October 25 – 31, 2014
Please click here for general information on concrete pours.
Saturday, October 25
- Dominus construction crew doing housekeeping work on-site, from 9:00 am.
- Electrical and plumbing contractors working in the building from 9:00 am.
Monday, October 27
- 24thFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
- Window delivery starting at 9:00am, south curb lane of The Esplanade will be occupied. from 2:00 pm to 5:00 pm
Tuesday, October 28
- Rebar delivery from 7:00 am.
- 24thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
Wednesday, October 29
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Thursday, October 30
- 24th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
Friday, October 31
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-October-25-31-2014