L Tower Update October 18 – 24
October 17, 2014 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower October 18 – 24, 2014
NOTE: New residents are continuing to move into the L Tower When moves occur they are loading in on Yonge Street. As external construction comes closer to completion, the dimensions of the future sidewalk area on the north side of The Esplanade is beginning to emerge.
- Please click the link to the right for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-October-18-24-2014
Saturday, October 18
- Interior work on site.
- Move-ins through the Yonge Street entrance.
Monday, October 20
- There will be general construction work inside the L Tower.
- Move-ins continue through the Yonge Street entrance.
Tuesday, October 21
- There will be general construction work inside the L Tower.
- Move-ins continue through the Yonge Street entrance.
Wednesday, October 22
- There will be general construction work inside the L Tower.
- Move-ins continue through the Yonge Street entrance.
Thursday, October 23
- There will be general construction work inside the L Tower.
- Move-ins continue through the Yonge Street entrance.
Friday, October 24
- There will be general construction work inside the L Tower.
- Move-ins continue through the Yonge Street entrance.