Backstage Construction Schedule October 18 – 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 18 – 24, 2014

 Please click here for general information on concrete pours

20141010_141125

Loading concrete at the Backstage construction site

Saturday, October 18

  • Window delivery starting at 9:00am, south curb lane of The Esplanade will be occupied. from 9:00 am. 

Monday, October 20

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, October 21

  • Rebar delivery from 7:00 am.
  • 23rdFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, October 22

  • 23rdFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Thursday, October 23

  • 23rd Floor slab concrete pour #3 – part 1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Friday, October 24

  • Rebar delivery from 7:00 am.
  • 23rd Floor slab concrete pour #3 – part 2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: