L Tower Update October 14 – 17
October 14, 2014 Leave a comment
This is the current construction schedule for 8 The Esplanade – L Tower October 14 – 17, 2014
NOTE: Initial occupants continue to move-in to the L Tower. Move-ins are loading in on Yonge Street. With the building close to being substantially completed, work continue on the sidewalks on Yonge Street and The Esplanade.
-
Please click the link to the right for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Ocotber-14-17-2014
Tuesday, October 14
- There will be general construction work inside the L Tower.
- Move-ins continue through the Yonge Street entrance.
Wednesday, October 15
- There will be general construction work inside the L Tower.
- Move-ins continue through the Yonge Street entrance.
Thursday, October 16
- There will be general construction work inside the L Tower.
- Move-ins continue through the Yonge Street entrance.
Friday, October 17
- There will be general construction work inside the L Tower.
- Move-ins continue through the Yonge Street entrance.