Backstage Construction Schedule November 1 – 7

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for November 1 – 7, 2014

 Please click here for general information on concrete pours

Backstage condominium October 31, 2014

Backstage condominium October 31, 2014

Saturday, November 1

  • Dominus construction crew doing housekeeping work on-site, from 9:00 am. 
  • Electrical and plumbing contractors working in the building from 9:00 am.

Monday, November 3

  • Rebar delivery from 7:00 am.
  • 25thFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Tuesday, November 4

  • Rebar delivery from 7:00 am.
  • 25thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, November 5

  • 25thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

ThursdayNovember 6

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Friday, November 7

  • 26th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower Update November 1 – 7

This is the current construction schedule for 8 The Esplanade – L Tower  November 1 – 7, 2014

NOTE: New residents are continuing to move into the L Tower When moves occur they are loading in on Yonge Street. As external construction comes closer to completion, the dimensions of the future sidewalk area on Yonge Street is emerging. 

Saturday, November 1

  • Interior work on site.
  • Move-ins through the Yonge Street entrance.

Monday, November 3

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Tuesday, November 4

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Wednesday, November 5

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Thursday, November 6

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Friday, November 7

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

    L Tower Yonge Street loading entrance

    L Tower Yonge Street loading entrance

Backstage Construction Schedule October 25 – 31

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 25 – 31, 2014

 Please click here for general information on concrete pours

Backstage with concrete bucket.

Backstage with concrete bucket.

Saturday, October 25

  • Dominus construction crew doing housekeeping work on-site, from 9:00 am. 
  • Electrical and plumbing contractors working in the building from 9:00 am.

Monday, October 27

  • 24thFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.
  • Window delivery starting at 9:00am, south curb lane of The Esplanade will be occupied. from 2:00 pm to 5:00 pm

Tuesday, October 28

  • Rebar delivery from 7:00 am.
  • 24thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, October 29

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Thursday, October 30

  • 24th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Friday, October 31

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower Update October 25 – 31

This is the current construction schedule for 8 The Esplanade – L Tower  October 25 – 31, 2014

NOTE: New residents are continuing to move into the L Tower When moves occur they are loading in on Yonge Street. As external construction comes closer to completion, the dimensions of the future sidewalk area on the north side of The Esplanade is beginning to emerge.  

Saturday, October 25

  • Interior work on site.
  • Move-ins through the Yonge Street entrance.

Monday, October 27

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Tuesday, October 28

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Wednesday, October 29

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Thursday, October 30

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Friday, October 31

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Backstage Construction Schedule October 18 – 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 18 – 24, 2014

 Please click here for general information on concrete pours

20141010_141125

Loading concrete at the Backstage construction site

Saturday, October 18

  • Window delivery starting at 9:00am, south curb lane of The Esplanade will be occupied. from 9:00 am. 

Monday, October 20

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, October 21

  • Rebar delivery from 7:00 am.
  • 23rdFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, October 22

  • 23rdFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Thursday, October 23

  • 23rd Floor slab concrete pour #3 – part 1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Friday, October 24

  • Rebar delivery from 7:00 am.
  • 23rd Floor slab concrete pour #3 – part 2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower Update October 18 – 24

This is the current construction schedule for 8 The Esplanade – L Tower  October 18 – 24, 2014

NOTE: New residents are continuing to move into the L Tower When moves occur they are loading in on Yonge Street. As external construction comes closer to completion, the dimensions of the future sidewalk area on the north side of The Esplanade is beginning to emerge.  

L Tower at 8 The Eslpanade

L Tower at 8 The Esplanade

Saturday, October 18

  • Interior work on site.
  • Move-ins through the Yonge Street entrance.

Monday, October 20

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Tuesday, October 21

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Wednesday, October 22

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Thursday, October 23

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Friday, October 24

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Backstage Construction Schedule October 14 – 17

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 14 – 17, 2014

 Please click here for general information on concrete pours

Concrete bucket being raised at Backstage.

Concrete bucket being raised at Backstage..

Tuesday, October 14

  • Rebar delivery from 7:00 am.
  • 22ndFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 11:00 am.
  • An after-slab wall and column concrete pour (45 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Wednesday, October 15

  • 22ndFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Thursday, October 16

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Friday, October 17

  • Rebar delivery from 7:00 am.
  • 22ndFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 11:00 am.
  • Tentative: An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower Update October 14 – 17

This is the current construction schedule for 8 The Esplanade – L Tower  October 14 – 17, 2014

NOTE: Initial occupants continue to move-in to the L Tower. Move-ins are loading in on Yonge Street. With the building close to being substantially completed, work continue on the sidewalks on Yonge Street and The Esplanade. 

Tuesday, October 14

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Wednesday, October 15

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Thursday, October 16

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Friday, October 17

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Backstage Construction Schedule October 11 – 13

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 11 – 13, 2014

 Please click here for general information on concrete pours

Saturday, October 11

  • Dominus construction doing housekeeping work on site, from 9:00 am.

Monday, October 13 – Site Closed for Thanksgiving 

Backstage condo, October 10, 2014

Backstage condo, October 10, 2014

NOTE: The construction update for Tuesday, October 14 – Friday, October 17, will be posted by Tuesday morning, October 14. 

L Tower Update October 11 – 13

This is the current construction schedule for 8 The Esplanade – L Tower  October 11 – 13, 2014

NOTE: Initial occupants have begun to move-in to the L Tower. Moves are loading in on Yonge Street. With the building close to being substantially completed, work will begin in the coming weeks on the sidewalks on Yonge Street and The Esplanade. 

L Tower October 10

L Tower & CN Tower October 10, 2014

Saturday, October 11

  • Some interior work on site.

Monday, October 13 – Site Closed for the Thanksgiving Holiday! 

NOTE: The construction update for Tuesday, October 14 – Friday, October 17, will be posted by Tuesday morning, October 14. 

%d bloggers like this: