Backstage Construction Schedule September 27 – October 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 27 – October 3, 2014.

Cement Truck at Backstage

Cement Truck at Backstage

 Please click here for general information on concrete pours

Saturday, September 27

  • Dominus construction doing housekeeping work on site, from 9:00 am.
  • Subcontractor Italform flying in formwork and laying rebar in place, from 9:00 am. 

Monday, September 29

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, September 30

  • Rebar delivery from 7:00 am.
  • 20th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Wednesday, October 1

  • 20th  Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Thursday, October 2

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Friday, October 3

  • Rebar delivery from 7:00 am.
  • 20th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: