Backstage Construction Schedule September 22 – 26
September 19, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for September 22 – 26, 2014.
Please click here for general information on concrete pours.
Monday, September 22
- 18th Floor slab concrete pour #3, PART 2, by subcontractor Italform, scheduled to begin at 11:00 am.
- An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Tuesday, September 23
- Rebar delivery from 7:00 am.
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Wednesday, September 24
- 19th Floor slab concrete pour #1, PART 1, by subcontractor Italform, scheduled to begin at 11:00 am.
- An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Thursday, September 25
- 19th Floor slab concrete pour #1, PART 2, by subcontractor Italform, scheduled to begin at 11:00 am.
- An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Friday, September 26
- Rebar delivery from 7:00 am.
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-September-20-26-2014