Backstage Construction Schedule September 13 – 19
September 18, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for September 13 – 19, 2014. UPDATED September 18.
Please click here for general information on concrete pours.
Saturday, September 13
- Protective platform to be raised , by subcontractor Italform, scheduled to begin at 9:00 am.
- Dominus crew testing the internal hoist and doing housekeeping duties on-site.
Monday, September 15
- 17th Floor slab concrete pour #3, PART 2, by subcontractor Italform, scheduled to begin at 11:30 am.
- An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Tuesday, September 16
- Rebar delivery from 7:00 am.
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Wednesday, September 17
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Thursday, September 18
- 18th Floor slab concrete pour #1, PART 1, by subcontractor Italform, scheduled to begin at 11:30 am.
- An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
- NEW: Subcontractor, Italform will be raising the crane 3 storeys between 3 pm and 7 pm.
- Concrete Finishing until to 10:30 pm.
Friday, September 19
- Rebar delivery from 7:00 am.
- 18th Floor slab concrete pour #1, PART 2, by subcontractor Italform, scheduled to begin at 11:30 am.
- An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
- NEW: Toro Aluminum will be delivering a tractor trailer load of windows starting at 3:00 pm and running until 7:00 pm
- Concrete Finishing until to 10:30 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-September-13-19-2014