Backstage Construction Schedule September 13 – 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 13 – 19, 2014. UPDATED September 18.

Backstage condominium first floor of windows installed.

Backstage condominium first floor of windows installed.

 Please click here for general information on concrete pours

Saturday, September 13

  • Protective platform to be raised , by subcontractor Italform, scheduled to begin at 9:00 am.
  • Dominus crew testing the internal hoist and doing housekeeping duties on-site.

Monday, September 15

  • 17th Floor slab concrete pour #3, PART 2, by subcontractor Italform, scheduled to begin at 11:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Tuesday, September 16

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, September 17

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Thursday, September 18

  • 18th  Floor slab concrete pour #1, PART 1, by subcontractor Italform, scheduled to begin at 11:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
  • NEW: Subcontractor, Italform will be raising the crane 3 storeys between 3 pm and 7 pm.
  • Concrete Finishing until to 10:30 pm.

Friday, September 19

  • Rebar delivery from 7:00 am.
  • 18th Floor slab concrete pour #1, PART 2, by subcontractor Italform, scheduled to begin at 11:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
  • NEW: Toro Aluminum will be delivering a tractor trailer load of windows starting at 3:00 pm and running until 7:00 pm
  • Concrete Finishing until to 10:30 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: