Backstage Construction Schedule September 6 – 12
September 5, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for September 6 – 12, 2014. Please click here for general information on concrete pours.
Saturday, September 6
- 16th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 9:15 am.
- An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
- Also, following the slab pour, Toro Aluminum will be delivering 10th floor windows, till 4:00 pm.
- Concrete Finishing until to 8:30 pm.
Monday, September 8
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Tuesday, September 9
- Rebar delivery from 7:00 am.
- 17th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Wednesday, September 10
- 17th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Thursday, September 11
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Friday, September 12
- Rebar delivery from 7:00 am.
- 17th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:30 am.
- An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-September-6-12-2014