Backstage Construction Schedule September 27 – October 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 27 – October 3, 2014.

Cement Truck at Backstage

Cement Truck at Backstage

 Please click here for general information on concrete pours

Saturday, September 27

  • Dominus construction doing housekeeping work on site, from 9:00 am.
  • Subcontractor Italform flying in formwork and laying rebar in place, from 9:00 am. 

Monday, September 29

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, September 30

  • Rebar delivery from 7:00 am.
  • 20th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Wednesday, October 1

  • 20th  Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Thursday, October 2

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Friday, October 3

  • Rebar delivery from 7:00 am.
  • 20th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

L Tower Construction Schedule September 27 – October 3

This is the current construction schedule for 8 The Esplanade – L Tower  – September 27 – October 3, 2014

NOTE: Initial occupants are beginning to arrange their move-ins to the L Tower. When moves occur they will be loading in on Yonge Street, with no expected impacts on The Esplanade. With the building close to being substantially completed, work will begin in the coming weeks on the sidewalks, starting on the Yonge Street side of the project. 

 

L Tower on The Esplanade

L Tower on The Esplanade

Saturday, September 27

  • Interior work on site.

Monday, September 29

  • There will be general construction work inside the L Tower.
  •  Window wall installation.

Tuesday, September 30

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Wednesday, October 1

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Thursday, October 2

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Friday, October 3

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Backstage Construction Schedule Saturday, September 20

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for Saturday, September 20

Backstage windows in black & white.

Backstage windows in black & white.

Saturday, September 20

  • Toro Aluminum will be delivering a tractor trailer load of windows starting at 1:00 pm and running until 5:00 pm.
  • Italform with small crew raising platform on south side from 9:00 am.
  • Dominus doing housekeeping from 9:00 am.

L Tower Construction Schedule September 20 – 26

This is the current construction schedule for 8 The Esplanade – L Tower  – September 20 – 16, 2014

As we noted in an earlier post, move-ins to the L Tower may begin this week; more information will be posted when relevant and available. 
L Tower B x W

 

Saturday, September 20

  • Some interior work on site.
  • Window wall installation.

Monday, September 22

  • There will be general construction work inside the L Tower.
  •  Window wall installation.

Tuesday, September 23

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Wednesday, September 24

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Thursday, September 25

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Friday, September 26

  • There will be general construction work inside the L Tower.
  • Window wall installation.

L Tower move-ins to begin the week of September 22

The construction management team has advised us that move-ins are slated to begin the week of September 22, 2014 at the L Tower. Stay tuned for updates. 

L Tower from Hanlan's Point Ferry Dock

L Tower from Hanlan’s Point Ferry Dock

 

Backstage Construction Schedule September 22 – 26

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 22 – 26, 2014.

 Please click here for general information on concrete poursBackstage and concrete truck

Monday, September 22

  • 18th Floor slab concrete pour #3, PART 2, by subcontractor Italform, scheduled to begin at 11:00 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Tuesday, September 23

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, September 24

  • 19th  Floor slab concrete pour #1, PART 1, by subcontractor Italform, scheduled to begin at 11:00 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Thursday, September 25

  • 19th Floor slab concrete pour #1, PART 2, by subcontractor Italform, scheduled to begin at 11:00 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Friday, September 26

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule September 13 – 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 13 – 19, 2014. UPDATED September 18.

Backstage condominium first floor of windows installed.

Backstage condominium first floor of windows installed.

 Please click here for general information on concrete pours

Saturday, September 13

  • Protective platform to be raised , by subcontractor Italform, scheduled to begin at 9:00 am.
  • Dominus crew testing the internal hoist and doing housekeeping duties on-site.

Monday, September 15

  • 17th Floor slab concrete pour #3, PART 2, by subcontractor Italform, scheduled to begin at 11:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Tuesday, September 16

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, September 17

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Thursday, September 18

  • 18th  Floor slab concrete pour #1, PART 1, by subcontractor Italform, scheduled to begin at 11:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
  • NEW: Subcontractor, Italform will be raising the crane 3 storeys between 3 pm and 7 pm.
  • Concrete Finishing until to 10:30 pm.

Friday, September 19

  • Rebar delivery from 7:00 am.
  • 18th Floor slab concrete pour #1, PART 2, by subcontractor Italform, scheduled to begin at 11:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
  • NEW: Toro Aluminum will be delivering a tractor trailer load of windows starting at 3:00 pm and running until 7:00 pm
  • Concrete Finishing until to 10:30 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage Crane Rising 3 storeys on Thursday

The crane at the Backstage Condominium will be raised three (3) storeys on Thursday, September 18. The work will be done by subcontractor Italform and is scheduled to take place between 3 pm and 7 pm.

Backstage Crane to be raised 3 additional storeys on September 18.

Backstage Crane to be raised 3 additional storeys on September 18.

 

L Tower Construction Schedule September 13 – 19

This is the current construction schedule for 8 The Esplanade – L Tower  – September 13 – 19, 2014

L Tower September 12, 2014

L Tower September 12, 2014

Saturday, September 13

  • Some interior work on site.
  • Window wall installation.

Monday, September 15

  • There will be general construction work inside the L Tower.
  •  Window wall installation.

Tuesday, September 16

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Wednesday, September 17

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Thursday, September 18

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Friday, September 19

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Backstage Construction Schedule September 6 – 12

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 6 – 12, 2014.             Please click here for general information on concrete pours

20140828_104742

Backstage Crane

Saturday, September 6

  • 16th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 9:15 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Also, following the slab pour, Toro Aluminum will be delivering 10th floor windows, till 4:00 pm.
  • Concrete Finishing until to 8:30 pm.

Monday, September 8

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, September 9

  • Rebar delivery from 7:00 am.
  • 17th  Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Wednesday, September 10

  • 17th  Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Thursday, September 11

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Friday, September 12

  • Rebar delivery from 7:00 am.
  • 17th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.