Backstage Construction Schedule September 27 – October 3
September 26, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for September 27 – October 3, 2014.
Please click here for general information on concrete pours.
Saturday, September 27
- Dominus construction doing housekeeping work on site, from 9:00 am.
- Subcontractor Italform flying in formwork and laying rebar in place, from 9:00 am.
Monday, September 29
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Tuesday, September 30
- Rebar delivery from 7:00 am.
- 20th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Wednesday, October 1
- 20th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Thursday, October 2
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Friday, October 3
- Rebar delivery from 7:00 am.
- 20th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-September-27-Ocotber-3-2014