Backstage Construction Schedule – August 30 – September 5

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 30 – September 5, 2014.             Please click here for general information on concrete pours

 

The crane in action at Backstage condominium, August 28, 2014

The crane in action at Backstage condominium, August 28, 2014

Saturday, August 30

  • A Italform crew working on the Protective Platform on the south side for the building from 9:00 am – 3:00 pm. 
  • A Dominus Construction crew doing housekeeping on-site from from 9:00 am – 2:00 pm. 

Monday, September 1 – Labour Day – SITE CLSOED FOR THE HOLIDAY

Tuesday, September 2

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, September 3

  • 16th  Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Thursday, September 4

  • 16th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Friday, September 5

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: