Backstage Construction Schedule – August 16 – 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 16 – 22, 2014.

Please click here for general information on concrete pours.

 

Backstage August 15, 2014

Backstage August 15, 2014

Saturday, August 16

  • A 12-person forming crew from subcontractor Italform, will be on site working from 9:00 am.

Monday, August 18

  • A  wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, August 19

  • Rebar delivery from 7:00 am.
  • 14th  Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, August 20

  • 14th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Thursday, August 21 

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Friday, August 22

  • Rebar delivery from 7:00 am.
  • 14th  Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: